14549 W SAYRE ST 91342
Certificate Information: 14549 W SAYRE ST 91342
- Application / Permit
- 24016-20000-17123
- Plan Check / Job No.
- B24VN07308
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE WITH NEW ADDITION INTO A NEW ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) AMD (d). WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 2/24/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/3/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2024 | ALFRED RAMIREZ |
| Building Plans Picked Up | 6/13/2024 | APPLICANT |
| Corrections Issued | 6/14/2024 | ALFRED RAMIREZ |
| Issued | 2/24/2025 | APPLICANT |
| CofO in Progress | 1/22/2026 | JENNIFER RABUCHIN |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
| CofO Issued | 2/3/2026 | RUBEN SALAS |
| Permit Finaled | 2/3/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/30/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 7/30/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/30/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/31/2024 | LEE GUILBEAUX |
| Construction near power lines | Cleared | 12/4/2024 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/4/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/4/2025 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 3/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/4/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 4/25/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/2/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/2/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/9/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 5/9/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/9/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 5/21/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 5/21/2025 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 6/12/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 6/12/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Special/Order Compliance | 6/12/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 7/15/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 1/6/2026 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 1/6/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/6/2026 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/6/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 1/6/2026 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/15/2026 | Approved | JENNIFER RABUCHIN |
| Final | 1/15/2026 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/15/2026 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/15/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | JENNIFER RABUCHIN |