8954-8956 N EAMES AVE 91324

Certificate Information: 8954-8956 N EAMES AVE 91324

Application / Permit
24016-20000-17116
Plan Check / Job No.
B24VN07303
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE AND PORTION OF SINGLE FAMILY DWELLING TO A (N) JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) AND 65852.22. CONVERT CLOSET TO A (N) 1/2 BATHROOM IN SINGLE FAMILY DWELLING.
Permit Issued
Issued on 7/4/2024
Issuing Office
Current Status
CofO Issued on 2/25/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 GIOVANNY CHAVEZ
Corrections Issued 5/31/2024 GIOVANNY CHAVEZ
Plan Check Approved 7/4/2024 GIOVANNY CHAVEZ
Issued 7/4/2024 APPLICANT
CofO in Progress 2/23/2026 DAVID SCANTLIN
Permit Finaled 2/25/2026 JOHN JANSON
CofO Issued 2/25/2026 JOHN JANSON
Permit Finaled 2/25/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/26/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/26/2024 CARLOS RAMIREZ
Sewer availability Cleared 6/26/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 1171 JUSTIN AVE APT 3      GLENDALE, CA 91201

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2024 Partial Inspection KRISTEN CAUSEY
Footing/Foundation/Slab 5/19/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 5/21/2025 Not Ready for Inspection KRISTEN CAUSEY
Underground Mechanical 5/23/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 6/20/2025 Approved KRISTEN CAUSEY
HVAC-Rough 6/20/2025 Approved KRISTEN CAUSEY
PLUMBING-Rough 6/20/2025 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 6/25/2025 Partial Approval KRISTEN CAUSEY
Insulation 7/2/2025 Not Ready for Inspection KRISTEN CAUSEY
Insulation 7/8/2025 Not Ready for Inspection KRISTEN CAUSEY
Insulation 7/16/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 7/16/2025 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 7/28/2025 Approved DAVID SCANTLIN
Drywall Nailing 7/28/2025 Approved DAVID SCANTLIN
Green Building Rough 7/28/2025 Approved DAVID SCANTLIN
Shower Pan 8/19/2025 Approved KRISTEN CAUSEY
Shower Pan 8/21/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/6/2025 Approved CHRIS CHRISTENSEN
Final 11/12/2025 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 11/12/2025 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Not Ready DAVID SCANTLIN
Smoke Detectors 11/12/2025 Approved DAVID SCANTLIN
Final 12/23/2025 No Access for Inspection DAVID SCANTLIN
Green Building Final 12/23/2025 No Access for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Not Ready DAVID SCANTLIN
Final 1/13/2026 Corrections Issued DAVID SCANTLIN
Green Building Final 1/13/2026 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Approved DAVID SCANTLIN
Final 2/23/2026 OK to Issue CofO DAVID SCANTLIN
Service/Power Release 2/23/2026 Approved DAVID SCANTLIN