10400-10402 N EDGEBROOK WAY 91326

Certificate Information: 10400-10402 N EDGEBROOK WAY 91326

Application / Permit
24016-20000-16709
Plan Check / Job No.
B24VN07133
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) LIVING ROOM TO ACCESSORY DWELING UNIT PER GCS 65852.2(e)(1)(A) FOR CONVERSION OF PORTION OF EXISITNG SFD ONLY.
Permit Issued
Issued on 9/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/28/2024 PINANK PATEL
Corrections Issued 5/28/2024 PINANK PATEL
Building Plans Picked Up 5/30/2024 APPLICANT
Plan Check Approved 9/19/2024 ALEC MOUSAKHANIAN
Issued 9/19/2024 APPLICANT
CofO in Progress 4/16/2025 DAVID SCANTLIN
CofO Issued 4/16/2025 JOHN JANSON
Permit Finaled 4/16/2025 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 6/6/2024 OSCAR CASTRO
Address approval Cleared 6/12/2024 BIAINA HARITUNIAN
Miscellaneous Cleared 6/12/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/12/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/27/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/3/2024 Approved DAVID SCANTLIN
Pre-Inspection 10/11/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 11/1/2024 Not Ready for Inspection DAVID SCANTLIN
Pre-Inspection 12/11/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 1/10/2025 Partial Approval DAVID SCANTLIN
Sewer 1/10/2025 Approved DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 1/15/2025 No Access for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 1/23/2025 Not Ready for Inspection SCOTT SOBEL
PLUMBING-Rough 1/23/2025 Not Ready for Inspection SCOTT SOBEL
BUILDING-Rough-Frame 2/6/2025 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 2/6/2025 Approved DAVID SCANTLIN
Green Building Rough 2/6/2025 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 2/6/2025 Approved DAVID SCANTLIN
Drywall Nailing 2/19/2025 Partial Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Approved SCOTT SOBEL
Insulation 2/19/2025 Approved SCOTT SOBEL
Drywall Nailing 2/24/2025 Approved DAVID SCANTLIN
Shower Pan 2/24/2025 Approved DAVID SCANTLIN
Interior/Exterior Lathing 2/26/2025 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 3/25/2025 Approved DAVID SCANTLIN
Final 3/25/2025 Corrections Issued DAVID SCANTLIN
Green Building Final 3/25/2025 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 3/25/2025 Approved DAVID SCANTLIN
Final 4/16/2025 OK to Issue CofO DAVID SCANTLIN
Green Building Final 4/16/2025 Approved DAVID SCANTLIN