919 N CRESCENT HEIGHTS BLVD 90046

Certificate Information: 919 N CRESCENT HEIGHTS BLVD 90046

Application / Permit
24016-20000-16694
Plan Check / Job No.
B24VN07127
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 10/4/2024
Issuing Office
Valley
Current Status
CofO Issued on 7/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/24/2024 JEROME MAGAT PALMA
Corrections Issued 5/24/2024 JEROME MAGAT PALMA
Building Plans Picked Up 5/30/2024 APPLICANT
Plan Check Approved 7/16/2024 KAMYAR EMAMI
Issued 10/4/2024 APPLICANT
CofO in Progress 7/8/2025 JOSE MACIAS
Permit Finaled 7/15/2025 DEROLD HAUFF
CofO Issued 7/15/2025 DEROLD HAUFF
Permit Finaled 7/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/6/2024 JUSTIN BICOL
Sewer availability Cleared 6/6/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 6/10/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 6/14/2024 JUSTIN BICOL
Construction near power lines Cleared 7/16/2024 ENRIQUE ACOSTA

Contact Information

Contractor New Generation Home Improvements Inc; Lic. No.: 938552-B 5805 WHITE OAK AVE #18431      ENCINO, CA 91416
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/15/2024 Approved JOSE MACIAS
Footing/Foundation/Slab 10/21/2024 Corrections Issued JOSE MACIAS
Footing/Foundation/Slab 11/19/2024 Corrections Issued JOSE MACIAS
Sewer 12/12/2024 Partial Approval JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Approved JOSE MACIAS
Sewer 12/20/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 1/21/2025 Approved JOSE MACIAS
HVAC-Rough 1/21/2025 Approved JOSE MACIAS
PLUMBING-Rough 1/21/2025 Approved JOSE MACIAS
Wood Frame 1/21/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 1/27/2025 Approved JOSE MACIAS
Insulation 2/12/2025 Approved JOSE MACIAS
Interior/Exterior Lathing 2/12/2025 Approved JOSE MACIAS
Drywall Nailing 2/24/2025 Approved AMY COLIN
Insulation 2/24/2025 Approved AMY COLIN
BUILDING-Rough-Frame 6/6/2025 Approved JOSE MACIAS
Final 6/6/2025 Corrections Issued JOSE MACIAS
Green Building Final 6/6/2025 Approved JOSE MACIAS
Green Building Rough 6/6/2025 Approved JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Not Required JOSE MACIAS
Smoke Detectors 6/6/2025 Approved JOSE MACIAS
Final 6/12/2025 OK to Issue CofO JOSE MACIAS
Service/Power Release 7/8/2025 Approved JOSE MACIAS