919 N CRESCENT HEIGHTS BLVD 90046
Certificate Information: 919 N CRESCENT HEIGHTS BLVD 90046
- Application / Permit
- 24016-20000-16694
- Plan Check / Job No.
- B24VN07127
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/4/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 5/24/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 5/30/2024 | APPLICANT |
| Plan Check Approved | 7/16/2024 | KAMYAR EMAMI |
| Issued | 10/4/2024 | APPLICANT |
| CofO in Progress | 7/8/2025 | JOSE MACIAS |
| Permit Finaled | 7/15/2025 | DEROLD HAUFF |
| CofO Issued | 7/15/2025 | DEROLD HAUFF |
| Permit Finaled | 7/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 6/6/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 6/10/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 7/16/2024 | ENRIQUE ACOSTA |
Contact Information
| Contractor | New Generation Home Improvements Inc; Lic. No.: 938552-B | 5805 WHITE OAK AVE #18431 ENCINO, CA 91416 |
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/15/2024 | Approved | JOSE MACIAS |
| Footing/Foundation/Slab | 10/21/2024 | Corrections Issued | JOSE MACIAS |
| Footing/Foundation/Slab | 11/19/2024 | Corrections Issued | JOSE MACIAS |
| Sewer | 12/12/2024 | Partial Approval | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2024 | Approved | JOSE MACIAS |
| Sewer | 12/20/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 1/21/2025 | Approved | JOSE MACIAS |
| HVAC-Rough | 1/21/2025 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 1/21/2025 | Approved | JOSE MACIAS |
| Wood Frame | 1/21/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 1/27/2025 | Approved | JOSE MACIAS |
| Insulation | 2/12/2025 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 2/12/2025 | Approved | JOSE MACIAS |
| Drywall Nailing | 2/24/2025 | Approved | AMY COLIN |
| Insulation | 2/24/2025 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 6/6/2025 | Approved | JOSE MACIAS |
| Final | 6/6/2025 | Corrections Issued | JOSE MACIAS |
| Green Building Final | 6/6/2025 | Approved | JOSE MACIAS |
| Green Building Rough | 6/6/2025 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 6/6/2025 | SGSOV Not Required | JOSE MACIAS |
| Smoke Detectors | 6/6/2025 | Approved | JOSE MACIAS |
| Final | 6/12/2025 | OK to Issue CofO | JOSE MACIAS |
| Service/Power Release | 7/8/2025 | Approved | JOSE MACIAS |