739 N HANLEY AVE 90049
Certificate Information: 739 N HANLEY AVE 90049
- Application / Permit
- 24016-20000-16477
- Plan Check / Job No.
- B24VN07012
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PARITAL PILE AND GRADE BEAM UNDERPINNING. GARAGE FOUNDATION REPLACEMENT AND REPAIR OF (E) FRAMING PER ENG DETAIL. FUTURE DECK EXT FOUNDATION
- Permit Issued
- Issued on 1/15/2025
- Issuing Office
- Current Status
- Issued on 1/15/2025
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | PETER MOSESIAN |
| Corrections Issued | 5/25/2024 | PETER MOSESIAN |
| Quality Review Completed | 5/29/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/31/2024 | APPLICANT |
| Plan Check Approved | 7/5/2024 | PETER MOSESIAN |
| Issued | 1/15/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/5/2024 | PETER MOSESIAN |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Aparicio,, Daniel Gonzalo; Lic. No.: C92121 | 19332 AVENIDA DEL SOL WALNUT, CA 91789 |
| Engineer | Hamilton,, David; Lic. No.: GE2721 | 1641 BORDER AVE TORRANCE, CA 90501 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/5/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 2/11/2025 | No Access for Inspection | KENNETH NAGLE |
| Deputy Other (see comments) | 3/6/2025 | No Access for Inspection | MATTHEW JENKINS |
| Excavation/Setback/Form/Re-Bar | 3/6/2025 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/10/2025 | Not Ready for Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 3/12/2025 | Partial Approval | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/25/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/26/2025 | Corrections Issued | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 3/27/2025 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/8/2025 | Approved | KEVIN SARGSYAN |
| Wood Frame | 4/8/2025 | Corrections Issued | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 4/9/2025 | Conditional Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Corrections Issued | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Ready | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2025 | Corrections Issued | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2025 | Approved | KEVIN SARGSYAN |