20333-20335 W GRESHAM ST 91306

Certificate Information: 20333-20335 W GRESHAM ST 91306

Application / Permit
24016-20000-15661
Plan Check / Job No.
B24VN06630
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 7/1/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/20/2024 MADISON ODELL
Corrections Issued 5/20/2024 MADISON ODELL
Building Plans Picked Up 5/22/2024 APPLICANT
Applicant returned to address corrections 6/27/2024 DANIEL ABRAMYAN
Issued 7/1/2024 APPLICANT
CofO in Progress 11/18/2024 CHRIS CHRISTENSEN
CofO Issued 12/11/2024 JOHN JANSON
Permit Finaled 12/11/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 6/5/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 6/5/2024 CARLOS RAMIREZ
Sewer availability Cleared 6/5/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mehdizadehnasrabadi,, Mohammad; Lic. No.: C85373 705 W 9TH STREET UNIT 2705      LOS ANGELES, CA 90015

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/29/2024 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 8/5/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 8/5/2024 Partial Approval JEFFREY HARTLINE
Sewer 8/5/2024 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 8/20/2024 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/24/2024 Approved CHRIS CHRISTENSEN
Gas Test 9/24/2024 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 9/24/2024 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Rough 9/24/2024 Approved CHRIS CHRISTENSEN
Wood Frame 9/24/2024 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/1/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 10/1/2024 Approved CHRIS CHRISTENSEN
Insulation 10/1/2024 Approved CHRIS CHRISTENSEN
Deputy Wood Construction 10/4/2024 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/8/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 10/8/2024 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/15/2024 Approved CHRIS CHRISTENSEN
Gas Test 10/15/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/15/2024 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/21/2024 Approved CHRIS CHRISTENSEN
Final 11/12/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/12/2024 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/12/2024 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/12/2024 Approved CHRIS CHRISTENSEN
Final 11/15/2024 OK to Issue CofO CHRIS CHRISTENSEN
Green Building Final 11/15/2024 Approved CHRIS CHRISTENSEN
Service/Power Release 11/15/2024 Approved CHRIS CHRISTENSEN