5408-5410 N BLANCO AVE 91367
Certificate Information: 5408-5410 N BLANCO AVE 91367
- Application / Permit
- 24016-20000-15651
- Plan Check / Job No.
- B24VN06620
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE AND IRREG SHAPED PORTION OF SFD TO JUNIOR ACCESSORY DWELLING UNIT (499 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- CofO Issued on 9/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 5/20/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 6/4/2024 | APPLICANT |
| Plan Check Approved | 7/16/2024 | ALEC MOUSAKHANIAN |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 9/25/2024 | TROY SANDERS |
| Permit Finaled | 9/27/2024 | JOHN JANSON |
| CofO Issued | 9/27/2024 | JOHN JANSON |
| Permit Finaled | 9/27/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/10/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 6/13/2024 | CHARLES POWELL |
Contact Information
| Contractor | Nesbou Homes; Lic. No.: 1045251-B | 19730 VENTURA BLVD SUITE 1 WOODLAND HILLS, CA 91364 |
| Engineer | Mroczka,, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/18/2024 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 7/18/2024 | Partial Approval | TROY SANDERS |
| Deputy Drilled-In Anchors | 7/24/2024 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 7/24/2024 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 8/2/2024 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 8/2/2024 | Approved | TROY SANDERS |
| HVAC-Rough | 8/2/2024 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 8/2/2024 | Approved | TROY SANDERS |
| Green Building Rough | 8/5/2024 | Approved | TROY SANDERS |
| HVAC-Rough | 8/5/2024 | Approved | TROY SANDERS |
| Insulation | 8/5/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 8/8/2024 | Approved | TROY SANDERS |
| Insulation | 8/8/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 8/9/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/9/2024 | Partial Approval | TROY SANDERS |
| Service/Power Release | 8/13/2024 | Approved | TROY SANDERS |
| Special/Order Compliance | 8/13/2024 | Approved | SCOTT SOBEL |
| Gas Test | 9/13/2024 | Approved | SCOTT SOBEL |
| Final | 9/18/2024 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 9/18/2024 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/18/2024 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/18/2024 | Approved | TROY SANDERS |
| Final | 9/24/2024 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 9/24/2024 | Approved | TROY SANDERS |