13972-13974 W DAVENTRY ST 91331

Certificate Information: 13972-13974 W DAVENTRY ST 91331

Application / Permit
24016-20000-15602
Plan Check / Job No.
B24VN06609
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. DETACHED RECREATION ROOM AND STORAGE INTO TWO ACCESSORY DWELLING UNITS PER GCS 65852.2(e)(1)(D) and LAMC 12.22 A.33(c), (d), and (g). "COMPLY WITH DEPARTMENT ORDER effective date 07/14/2016. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 8/16/2024
Issuing Office
Valley
Current Status
Issued on 8/16/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/10/2024 APPLICANT
Assigned to Plan Check Engineer 5/17/2024 ARTIN ZARUKIAN
Corrections Issued 5/18/2024 ARTIN ZARUKIAN
Building Plans Picked Up 6/13/2024 APPLICANT
Plan Check Approved 8/14/2024 ROSENDO MEDINA
Issued 8/16/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/5/2024 CARLOS AGUILERA
Miscellaneous Cleared 8/7/2024 BRENNEN OBETO
ZI Cleared 8/7/2024 BRENNEN OBETO
Eng Process Fee Ord 176,300 Cleared 8/12/2024 CARLOS AGUILERA
Sewer availability Cleared 8/12/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/9/2024 Conditional Approval ROBERT GOLD
BUILDING-Rough-Frame 12/31/2024 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Rough 12/31/2024 Partial Inspection MICHEL ABAJAN
Gas Test 12/31/2024 Partial Inspection MICHEL ABAJAN
Green Building Rough 12/31/2024 Partial Inspection MICHEL ABAJAN
METHANE-Rough 12/31/2024 Approved MICHEL ABAJAN
Pre-Inspection 12/31/2024 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 3/27/2025 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 3/27/2025 Not Ready for Inspection MICHEL ABAJAN
Gas Test 3/27/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 3/27/2025 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 4/18/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/18/2025 Approved MICHEL ABAJAN
Gas Test 4/18/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 4/18/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/16/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/16/2025 Approved MICHEL ABAJAN
Gas Test 6/16/2025 Approved MICHEL ABAJAN
Green Building Rough 6/16/2025 Approved MICHEL ABAJAN
HVAC-Rough 6/16/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 6/16/2025 Approved MICHEL ABAJAN
Insulation 7/7/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/7/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2025 Partial Approval MICHEL ABAJAN
Drywall Nailing 9/3/2025 Approved MICHEL ABAJAN
Shower Pan 9/3/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/9/2025 Approved MICHEL ABAJAN
Shower Pan 9/9/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/26/2026 Partial Inspection MICHEL ABAJAN
Pre-Inspection 1/26/2026 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 6/18/2026 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 6/24/2026 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 7/7/2026 Not Ready for Inspection MICHEL ABAJAN