17515-17517 W BURTON ST 91325

Certificate Information: 17515-17517 W BURTON ST 91325

Application / Permit
24016-20000-15469
Plan Check / Job No.
B24VN06533
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO A (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. WORK DONE PER WFPP.
Permit Issued
Issued on 11/5/2024
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2024 APPLICANT
Assigned to Plan Check Engineer 5/24/2024 GIOVANNY CHAVEZ
Corrections Issued 5/25/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 7/31/2024 MADISON ODELL
Applicant returned to address corrections 10/16/2024 MADISON ODELL
Plan Check Approved 10/29/2024 MADISON O'DELL
Issued 11/5/2024 APPLICANT
CofO in Progress 4/22/2025 SALVADOR MARTINEZ
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/3/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/3/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/18/2024 BIAINA HARITUNIAN

Contact Information

Architect , ; Lic. No.: C39815       GLENDALE, CA 91201
Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/25/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 2/25/2025 Partial Approval GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 2/26/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 2/27/2025 Corrections Issued SALVADOR MARTINEZ
Sewer 2/27/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 3/3/2025 Approved SALVADOR MARTINEZ
Sewer 3/3/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 3/11/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 3/11/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 3/11/2025 Not Ready for Inspection GAREN HAYRAPETYAN
PLUMBING-Rough 3/11/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 3/12/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 3/12/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 3/17/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 3/17/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 3/17/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 3/17/2025 Partial Approval GAREN HAYRAPETYAN
Insulation 3/19/2025 Approved SALVADOR MARTINEZ
Drywall Nailing 3/24/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 3/24/2025 Approved SALVADOR MARTINEZ
Final 4/3/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 4/3/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 4/3/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 4/3/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Final 4/7/2025 Corrections Issued SALVADOR MARTINEZ
Final 4/7/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Final 4/7/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Final 4/7/2025 Corrections Issued SALVADOR MARTINEZ
Final 4/17/2025 OK to Issue CofO SALVADOR MARTINEZ
Green Building Final 4/17/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 4/17/2025 SGSOV Not Required SALVADOR MARTINEZ
Smoke Detectors 4/17/2025 Approved SALVADOR MARTINEZ