7831 N SANCOLA AVE 91352
Certificate Information: 7831 N SANCOLA AVE 91352
- Application / Permit
- 24016-20000-15466
- Plan Check / Job No.
- B24VN06532
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 25'-7" X 18'-6" ADDITION TO & CONVERT (E) 329 SF DETACHED GARAGE TO (N) 773 SF ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENG. "COMPLY WITH DEPARTMENT ORDER effective date 04/16/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 6/17/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 5/16/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/20/2024 | APPLICANT |
| Plan Check Approved | 6/13/2024 | LUISANGEL VALENZUELA |
| Issued | 6/17/2024 | APPLICANT |
| CofO in Progress | 7/16/2025 | THOMAS WOODS |
| Permit Finaled | 1/30/2026 | DAVID JAMES |
| CofO Issued | 1/30/2026 | DAVID JAMES |
| Permit Finaled | 1/30/2026 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 5/20/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/20/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/30/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grigoryan,, Souren; Lic. No.: C93320 | 6506 TEESDALE AVE NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/26/2024 | Not Ready for Inspection | THOMAS WOODS |
| Underground Mechanical | 9/27/2024 | Approved | JOSE RUBIO |
| Footing/Foundation/Slab | 10/15/2024 | Approved | THOMAS WOODS |
| BUILDING-Rough-Frame | 12/9/2024 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 12/9/2024 | Approved | THOMAS WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Approved | THOMAS WOODS |
| Gas Test | 12/9/2024 | Approved | THOMAS WOODS |
| Green Building Rough | 12/9/2024 | Approved | THOMAS WOODS |
| HVAC-Rough | 12/9/2024 | Approved | THOMAS WOODS |
| MERV13>=Rough | 12/9/2024 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 12/9/2024 | Approved | THOMAS WOODS |
| Insulation | 12/31/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 12/31/2024 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 1/13/2025 | Approved | THOMAS WOODS |
| Shower Pan | 1/13/2025 | Approved | THOMAS WOODS |
| Drywall Nailing | 1/27/2025 | Approved | THOMAS WOODS |
| Sewer | 3/27/2025 | Corrections Issued | THOMAS WOODS |
| Underground Mechanical | 3/27/2025 | Not Ready for Inspection | THOMAS WOODS |
| Sewer | 4/1/2025 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 7/7/2025 | Not Ready for Inspection | THOMAS WOODS |
| Final | 7/7/2025 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 7/7/2025 | Not Ready for Inspection | THOMAS WOODS |
| HVAC-Final | 7/7/2025 | Not Ready for Inspection | THOMAS WOODS |
| MERV13>=Final | 7/7/2025 | Not Ready for Inspection | THOMAS WOODS |
| PLUMBING-Final | 7/7/2025 | Not Ready for Inspection | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/7/2025 | SGSOV Not Ready | THOMAS WOODS |
| Smoke Detectors | 7/7/2025 | Not Ready for Inspection | THOMAS WOODS |
| ELECTRICAL-Final | 7/11/2025 | Not Ready for Inspection | THOMAS WOODS |
| Final | 7/11/2025 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 7/11/2025 | Not Ready for Inspection | THOMAS WOODS |
| HVAC-Final | 7/11/2025 | Not Ready for Inspection | THOMAS WOODS |
| MERV13>=Final | 7/11/2025 | Not Ready for Inspection | THOMAS WOODS |
| PLUMBING-Final | 7/11/2025 | Not Ready for Inspection | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 7/11/2025 | SGSOV Approved | THOMAS WOODS |
| Smoke Detectors | 7/11/2025 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 7/15/2025 | Not Ready for Inspection | THOMAS WOODS |
| Final | 7/15/2025 | Not Ready for Inspection | THOMAS WOODS |
| Green Building Final | 7/15/2025 | Not Ready for Inspection | THOMAS WOODS |
| HVAC-Final | 7/15/2025 | Not Ready for Inspection | THOMAS WOODS |
| MERV13>=Final | 7/15/2025 | Not Ready for Inspection | THOMAS WOODS |
| PLUMBING-Final | 7/15/2025 | Not Ready for Inspection | THOMAS WOODS |
| ELECTRICAL-Final | 7/16/2025 | Approved | THOMAS WOODS |
| Final | 7/16/2025 | OK to Issue CofO | THOMAS WOODS |
| Gas Test | 7/16/2025 | Approved | THOMAS WOODS |
| Green Building Final | 7/16/2025 | Approved | THOMAS WOODS |
| HVAC-Final | 7/16/2025 | Approved | THOMAS WOODS |
| MERV13>=Final | 7/16/2025 | Approved | THOMAS WOODS |
| PLUMBING-Final | 7/16/2025 | Approved | THOMAS WOODS |