20441-20443 W CALIFA ST 91367
Certificate Information: 20441-20443 W CALIFA ST 91367
- Application / Permit
- 24016-20000-15447
- Plan Check / Job No.
- B24VN06516
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert existing attached garage to JADU per CA Govt. Code 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 5/23/2024
- Issuing Office
- Current Status
- CofO Issued on 5/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2024 | DANIEL SMILEY |
| Corrections Issued | 5/15/2024 | DANIEL SMILEY |
| Plan Check Approved | 5/22/2024 | MINA HABILI |
| Issued | 5/23/2024 | APPLICANT |
| CofO in Progress | 5/22/2025 | ALEXANDER HANDY |
| Permit Finaled | 5/30/2025 | JOHN JANSON |
| CofO Issued | 5/30/2025 | JOHN JANSON |
| Permit Finaled | 5/30/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 5/16/2024 | EDGAR ALCARAZ |
| ZA Case | Cleared | 5/16/2024 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2024 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 5/17/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Rodo Development Inc; Lic. No.: 1100805-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/2/2024 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 12/2/2024 | Conditional Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 12/2/2024 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 1/15/2025 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 1/15/2025 | Approved | ALEXANDER HANDY |
| Green Building Rough | 1/15/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 1/15/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| PLUMBING-Rough | 1/15/2025 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 1/29/2025 | Partial Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Approved | ALEXANDER HANDY |
| Insulation | 2/4/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 2/11/2025 | Partial Approval | JUAN ALVARADO |
| Interior/Exterior Lathing | 2/14/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 2/14/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 3/7/2025 | No Access for Inspection | KRISTEN CAUSEY |
| BUILDING-Rough-Frame | 5/5/2025 | Approved | ALEXANDER HANDY |
| Final | 5/5/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 5/5/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Rough | 5/5/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 5/5/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 5/21/2025 | Approved | ALEXANDER HANDY |
| Final | 5/21/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 5/21/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 5/21/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 5/21/2025 | Approved | ALEXANDER HANDY |