19950 W RINALDI ST 91326
Certificate Information: 19950 W RINALDI ST 91326
- Application / Permit
- 24016-20000-15183
- Plan Check / Job No.
- B24VN06360
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- ***ePlan*** Construction of a new Verizon cell site with antennas and cabinets screened on the rooftop behind new FRP screening
- Permit Issued
- Issued on 2/21/2025
- Issuing Office
- Current Status
- Permit Finaled on 7/3/2025
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | REZA HAGHIGHAT |
| Corrections Issued | 5/27/2024 | REZA HAGHIGHAT |
| Plan Check Approved | 9/20/2024 | CAROLEAN BASMA |
| Issued | 2/21/2025 | APPLICANT |
| Permit Finaled | 7/2/2025 | GREGORY POMISH |
Permit Application Clearance Information
| "D" conditions | Cleared | 7/11/2024 | LESLIE PEREZ |
| APC | Cleared | 7/11/2024 | LESLIE PEREZ |
| CPC | Cleared | 7/11/2024 | LESLIE PEREZ |
| Miscellaneous | Cleared | 7/11/2024 | LESLIE PEREZ |
| Miscellaneous | Cleared | 7/11/2024 | LESLIE PEREZ |
| Plan Approval | Cleared | 7/11/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 7/11/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 7/11/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 7/11/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 7/11/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 7/11/2024 | LESLIE PEREZ |
| ZA Case | Cleared | 7/11/2024 | LESLIE PEREZ |
| Specific Plan | Cleared | 9/9/2024 | OLGA AYALA |
Contact Information
| Architect | Fulsang,, Eric John; Lic. No.: NA30715 | , |
| Contractor | Butler America Llc; Lic. No.: 1001725-A | 3820 STATE STREET STE B SANTA BARBARA, CA 93105 |
| Engineer | Poole,, Richard John; Lic. No.: NA71869 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 3/18/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 3/19/2025 | Partial Inspection | DEANDRE HOFFMAN |
| Structural Steel Frame | 3/19/2025 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Masonry | 4/2/2025 | Conditional Approval | DEANDRE HOFFMAN |
| Wood Frame | 6/5/2025 | Approved | KENNETH ROBERTS |
| Final | 7/2/2025 | Permit Finaled | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 7/2/2025 | SGSOV No Gas | GREGORY POMISH |
| Smoke Detectors | 7/2/2025 | Approved | GREGORY POMISH |