10871 W WILLOW CREST PL 91604
Certificate Information: 10871 W WILLOW CREST PL 91604
- Application / Permit
- 24016-20000-14841
- Plan Check / Job No.
- X24VN05182
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Window (15 ) and door ( 4) change-out (same size & type) for residential buildings. Dual glazing, labeled and certified by National Fenestration Rating Council (NFRC), is required for doors and windows replaced in all residential buildings, three stories or less, per Title 24, Part 6, Section 150.2(b) 1B. Kitchen/bathroom (4 ) remodel for residential buildings (no structural changes). Replace drywall (no new walls added) for single family dwellings and duplexes only. Water damage, dry-rot repair less than 10% of replacement cost of residential buildings.
- Permit Issued
- Issued on 5/6/2024
- Issuing Office
- Current Status
- Issued on 5/6/2024
Permit Application Status History
| Issued | 5/6/2024 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/30/2024 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/30/2024 | Corrections Issued | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 8/5/2024 | Conditional Approval | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 8/22/2024 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 10/16/2024 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/28/2024 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 10/28/2024 | Approved | BRIAN SULLIVAN |
| Wood Frame | 10/28/2024 | Approved | BRIAN SULLIVAN |
| Insulation | 11/9/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 11/13/2024 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 11/19/2024 | Approved | BRIAN SULLIVAN |
| Final | 4/19/2025 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 4/19/2025 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 4/19/2025 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 4/25/2025 | Partial Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 4/25/2025 | Approved | BRIAN SULLIVAN |
| Final | 5/29/2025 | Corrections Issued | BRIAN SULLIVAN |
| Final | 7/23/2025 | Not Ready for Inspection | CRAIG VAUGHAN |