16404-16406 W RAYEN ST 91343

Certificate Information: 16404-16406 W RAYEN ST 91343

Application / Permit
24016-20000-14784
Plan Check / Job No.
B24VN06169
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 5/13/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 JESSE ARELLANO
Corrections Issued 5/11/2024 JESSE ARELLANO
Plan Check Approved 5/13/2024 GIOVANNY CHAVEZ
Issued 5/13/2024 APPLICANT
Building Plans Picked Up 5/13/2024 APPLICANT
CofO in Progress 11/20/2024 GAREN HAYRAPETYAN
Permit Finaled 12/10/2024 RUBEN SALAS
CofO Issued 12/10/2024 RUBEN SALAS
Permit Finaled 12/10/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/11/2024 BRYAN GODINEZ
Sewer availability Cleared 5/11/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/13/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/13/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 7/8/2024 Not Ready for Inspection RAUL OLAGI
Pre-Inspection 7/8/2024 Approved RAUL OLAGI
Footing/Foundation/Slab 7/23/2024 Approved RAUL OLAGI
PLUMBING-Rough 7/25/2024 Partial Approval RAUL OLAGI
Sewer 7/25/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/7/2024 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 8/7/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/7/2024 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 8/9/2024 Approved SALVADOR MARTINEZ
HVAC-Rough 8/9/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/9/2024 Approved SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 8/13/2024 Partial Approval RAUL OLAGI
HVAC-Rough 8/13/2024 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Not Ready for Inspection RAUL OLAGI
Insulation 8/16/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 8/16/2024 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 8/21/2024 Approved RAUL OLAGI
Green Building Rough 8/21/2024 Approved RAUL OLAGI
Drywall Nailing 8/31/2024 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/31/2024 Partial Approval CHRISTOPHER ROJAS
Shower Pan 8/31/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/24/2024 Approved MICHAEL CORTEZ
ELECTRICAL-Final 11/6/2024 Corrections Issued SALVADOR MARTINEZ
Final 11/6/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 11/6/2024 Not Ready for Inspection SALVADOR MARTINEZ
PLUMBING-Final 11/6/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 11/6/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 11/19/2024 Approved GAREN HAYRAPETYAN
Final 11/19/2024 OK to Issue CofO GAREN HAYRAPETYAN
Green Building Final 11/19/2024 Approved GAREN HAYRAPETYAN
HVAC-Final 11/19/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Final 11/19/2024 Approved GAREN HAYRAPETYAN