14832-14834 W LANARK ST 91402

Certificate Information: 14832-14834 W LANARK ST 91402

Application / Permit
24016-20000-14380
Plan Check / Job No.
B24VN05989
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Convert existing attached garage to ADU (363 s.f.) per GCS 65852.2(e)(1)(A). Work per WFPP.
Permit Issued
Issued on 5/31/2024
Issuing Office
Current Status
CofO Issued on 2/12/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2024 APPLICANT
Assigned to Plan Check Engineer 5/6/2024 NGHI SU
Corrections Issued 5/7/2024 NGHI SU
Applicant returned to address corrections 5/22/2024 KELVIN CHUONG
Plan Check Approved 5/29/2024 ADAM HEGAZI
Issued 5/31/2024 APPLICANT
CofO in Progress 1/26/2026 VINCENT HANLEY
Permit Finaled 2/12/2026 RUBEN SALAS
CofO Issued 2/12/2026 RUBEN SALAS
Permit Finaled 2/12/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/7/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/7/2024 LEE GUILBEAUX
Sewer availability Cleared 5/7/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/7/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/8/2025 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 1/8/2025 Partial Approval VINCENT HANLEY
Underground Mechanical 1/8/2025 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 1/14/2025 Approved VINCENT HANLEY
PLUMBING-Rough 1/14/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 4/22/2025 Partial Approval VINCENT HANLEY
Green Building Rough 4/22/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 6/10/2025 Partial Approval VINCENT HANLEY
Green Building Rough 6/10/2025 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 6/10/2025 Approved VINCENT HANLEY
Drywall Nailing 6/20/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 6/20/2025 Approved VINCENT HANLEY
Gas Test 6/20/2025 Approved VINCENT HANLEY
Green Building Rough 6/20/2025 Approved VINCENT HANLEY
HVAC-Rough 6/20/2025 Approved VINCENT HANLEY
Interior/Exterior Lathing 6/20/2025 Partial Approval VINCENT HANLEY
Insulation 7/14/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 7/17/2025 Approved LOUIS ESCOTO
Drywall Nailing 8/19/2025 Approved KEVIN BERBERYAN
Service/Power Release 8/19/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 12/23/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 12/23/2025 Approved VINCENT HANLEY
Final 12/23/2025 Corrections Issued VINCENT HANLEY
Green Building Final 12/23/2025 Approved VINCENT HANLEY
HVAC-Final 12/23/2025 Approved VINCENT HANLEY
PLUMBING-Final 12/23/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Approved VINCENT HANLEY
Smoke Detectors 12/23/2025 Approved VINCENT HANLEY
Final 1/23/2026 OK to Issue CofO VINCENT HANLEY