9682 N SUNLAND BLVD 91040

Certificate Information: 9682 N SUNLAND BLVD 91040

Application / Permit
24016-20000-14343
Plan Check / Job No.
B24VN05970
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO EXISTING SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. AUTOMATIC FIRE SPRINKLER SYSTEM.
Permit Issued
Issued on 7/23/2024
Issuing Office
Current Status
Permit Finaled on 7/24/2025

Permit Application Status History

Submitted 5/1/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 PINANK PATEL
Corrections Issued 5/4/2024 PINANK PATEL
Applicant returned to address corrections 6/13/2024 ALFRED RAMIREZ
Plan Check Approved 6/25/2024 ROSENDO MEDINA
Issued 7/23/2024 APPLICANT
Permit Finaled 7/23/2025 WILLIAM WREN

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/7/2024 CHARLES POWELL

Contact Information

Contractor Topchain Construction Inc; Lic. No.: 980258-B 15315 BAKER CANYON RD      CANYON COUNTRY, CA 91390
Engineer Keshishian,, Nejdeh Erik; Lic. No.: C38341 2654 RISA DR      GLENDALE, CA 91208

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/1/2024 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 11/1/2024 Corrections Issued DAVID ANDERSON
Pre-Inspection 11/1/2024 Approved DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 11/5/2024 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 11/5/2024 Not Ready for Inspection DAVID ANDERSON
Deputy Drilled-In Anchors 11/12/2024 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 11/15/2024 Approved DAVID ANDERSON
Footing/Foundation/Slab 11/15/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 12/4/2024 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 12/4/2024 Corrections Issued DAVID ANDERSON
Wood Frame 12/4/2024 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 1/17/2025 Partial Approval DAVID ANDERSON
Sewer 1/17/2025 Not Ready for Inspection DAVID ANDERSON
PLUMBING-Rough 2/20/2025 Approved DAVID ANDERSON
ELECTRICAL-Rough 2/28/2025 Approved DAVID ANDERSON
HVAC-Rough 2/28/2025 Approved DAVID ANDERSON
Insulation 2/28/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 2/28/2025 Partial Approval DAVID ANDERSON
PLUMBING-Rough 2/28/2025 Approved DAVID ANDERSON
BUILDING-Rough-Frame 3/24/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 3/24/2025 Approved DAVID ANDERSON
Wood Frame 3/24/2025 Approved DAVID ANDERSON
Insulation 3/26/2025 Approved DAVID ANDERSON
Drywall Nailing 4/2/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 4/4/2025 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 7/16/2025 Approved JACK KARGODORIAN
Final 7/16/2025 Corrections Issued JACK KARGODORIAN
HVAC-Final 7/16/2025 Approved JACK KARGODORIAN
PLUMBING-Final 7/16/2025 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Not Ready JACK KARGODORIAN
Smoke Detectors 7/16/2025 Approved JACK KARGODORIAN
Final 7/23/2025 Permit Finaled WILLIAM WREN
SGSOV-Seismic Gas S/O Valve 7/23/2025 SGSOV Approved WILLIAM WREN