5334-5336 N CLEON AVE 91601

Certificate Information: 5334-5336 N CLEON AVE 91601

Application / Permit
24016-20000-14337
Plan Check / Job No.
B24VN05965
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ePlan: Conversion and addition to existing attached garage to ADU per LAMC 12.22 A.33(c) and (e). Design per WFPP.
Permit Issued
Issued on 9/25/2024
Issuing Office
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 ALFREDO JARA
Corrections Issued 5/4/2024 ALFREDO JARA
Applicant returned to address corrections 5/26/2024 AMY GUEVARRA
Applicant returned to address corrections 6/1/2024 AMY GUEVARRA
Applicant returned to address corrections 7/17/2024 CAROLEAN BASMA
Plan Check Approved 7/24/2024 CAROLEAN BASMA
Plan Check Approved 9/23/2024 NEHEMIAS RAMOS
Issued 9/25/2024 APPLICANT
CofO in Progress 5/1/2025 JOSE AVILA
Permit Finaled 9/11/2025 RUBEN SALAS
CofO Issued 9/11/2025 RUBEN SALAS
Permit Finaled 9/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/20/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/20/2024 CARLOS AGUILERA
Sewer availability Cleared 5/20/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/21/2024 CARLOS AGUILERA
Tenant Habitability Plan Cleared 5/22/2024 ISMAEL HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2024 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 11/8/2024 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 11/12/2024 Partial Approval JOSE AVILA
METHANE-Subgrade 11/12/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/15/2024 Approved JOSE AVILA
Deputy Drilled-In Anchors 11/26/2024 Conditional Approval JUAN VALENZUELA
BUILDING-Rough-Frame 12/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/2/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
METHANE-Rough 12/2/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/9/2024 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/9/2024 Partial Approval JOSE AVILA
METHANE-Rough 12/9/2024 Approved JOSE AVILA
PLUMBING-Rough 12/9/2024 Corrections Issued JOSE AVILA
HVAC-Rough 12/11/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 12/11/2024 Partial Approval JOSE AVILA
Interior/Exterior Lathing 12/12/2024 Not Ready for Inspection MICHAEL CORTEZ
HVAC-Rough 12/16/2024 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 12/16/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 12/18/2024 Approved JOSE AVILA
HVAC-Rough 12/18/2024 Approved JOSE AVILA
PLUMBING-Rough 12/18/2024 Approved JOSE AVILA
Insulation 12/20/2024 Approved JOSE AVILA
Shower Pan 12/20/2024 Corrections Issued JOSE AVILA
Drywall Nailing 12/30/2024 Approved LOUIS ESCOTO
Green Building Rough 12/30/2024 Approved LOUIS ESCOTO
Interior/Exterior Lathing 12/30/2024 Approved LOUIS ESCOTO
Underground Mechanical 1/17/2025 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/3/2025 Approved JOSE AVILA
METHANE-Barrier 4/3/2025 Approved JOSE AVILA
METHANE-Subgrade 4/3/2025 Approved JOSE AVILA
Green Building Final 4/8/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Approved JOSE AVILA
Smoke Detectors 4/8/2025 Approved JOSE AVILA
ELECTRICAL-Final 4/16/2025 Approved JOSE AVILA
Final 4/16/2025 Corrections Issued JOSE AVILA
HVAC-Final 4/16/2025 Approved JOSE AVILA
PLUMBING-Final 4/16/2025 Approved JOSE AVILA
Service/Power Release 4/16/2025 Approved JOSE AVILA
Final 5/1/2025 OK to Issue CofO JOSE AVILA