16003 W PARTHENIA ST 91343
Certificate Information: 16003 W PARTHENIA ST 91343
- Application / Permit
- 24016-20000-14291
- Plan Check / Job No.
- B24VN05948
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) PER ENGINEERING
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- Current Status
- CofO Issued on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2024 | ALFRED RAMIREZ |
| Corrections Issued | 5/7/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 7/1/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 7/8/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 8/1/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 8/15/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 8/21/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 8/25/2024 | DANIEL ABRAMYAN |
| Issued | 8/27/2024 | APPLICANT |
| CofO in Progress | 7/11/2025 | KEVIN BERBERYAN |
| Permit Finaled | 7/15/2025 | RUBEN SALAS |
| Permit Finaled | 7/15/2025 | RUBEN SALAS |
| CofO Issued | 7/15/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/26/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 6/26/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/10/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 10/24/2024 | No Access for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 10/24/2024 | No Access for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 10/29/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/29/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 10/30/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/30/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Special/Order Compliance | 10/30/2024 | Partial Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 12/3/2024 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 12/3/2024 | Partial Approval | SALVADOR MARTINEZ |
| Pre-Inspection | 12/17/2024 | Approved | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 1/24/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 2/6/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 2/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 2/12/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 2/12/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 2/27/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 2/27/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 3/4/2025 | Partial Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 3/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 3/24/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 4/4/2025 | Conditional Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/14/2025 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Other (see comments) | 4/18/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 4/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 4/28/2025 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 4/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 4/30/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Insulation | 5/2/2025 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 5/2/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 5/6/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Insulation | 5/8/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 5/14/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 6/30/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Final | 6/30/2025 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 6/30/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 7/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Final | 7/8/2025 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/8/2025 | SGSOV Approved | SALVADOR MARTINEZ |
| Final | 7/10/2025 | OK to Issue CofO | KEVIN BERBERYAN |