8301 1/2 N VALJEAN AVE 91343

Certificate Information: 8301 1/2 N VALJEAN AVE 91343

Application / Permit
24016-20000-14151
Plan Check / Job No.
B24VN05879
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) RECREATION ROOM TO A (N) 2ND UNIT PER SB9. WORK DONE PER WFPP.
Permit Issued
Issued on 7/10/2024
Issuing Office
Current Status
CofO Issued on 6/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 GIOVANNY CHAVEZ
Corrections Issued 5/6/2024 GIOVANNY CHAVEZ
Plan Check Approved 6/10/2024 GIOVANNY CHAVEZ
Issued 7/10/2024 APPLICANT
CofO in Progress 3/8/2026 KIRK SANDERS
Permit Finaled 6/30/2026 RUBEN SALAS
CofO Issued 6/30/2026 RUBEN SALAS
Permit Finaled 6/30/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/11/2024 CARLOS AGUILERA
Sewer availability Cleared 5/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/14/2024 CARLOS AGUILERA
ZA Case Cleared 5/14/2024 NATHAN ROMINE
Senate Bill 9 Cleared 5/21/2024 NATHAN ROMINE
ZA Case Cleared 5/21/2024 NATHAN ROMINE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 10/31/2024 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 10/31/2024 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 11/12/2024 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 11/12/2024 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 11/15/2024 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 11/15/2024 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 1/28/2025 Partial Approval SALVADOR MARTINEZ
HVAC-Rough 1/28/2025 Partial Approval SALVADOR MARTINEZ
Drywall Nailing 4/2/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 4/2/2025 Corrections Issued SALVADOR MARTINEZ
Drywall Nailing 4/10/2025 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 5/28/2025 Approved MICHAEL CORTEZ
ELECTRICAL-Final 2/12/2026 Approved GAREN HAYRAPETYAN
PLUMBING-Final 2/12/2026 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/17/2026 Approved GAREN HAYRAPETYAN
Final 2/17/2026 Corrections Issued GAREN HAYRAPETYAN
Gas Test 2/17/2026 Approved GAREN HAYRAPETYAN
Smoke Detectors 2/17/2026 Approved GAREN HAYRAPETYAN
Final 3/6/2026 OK to Issue CofO KIRK SANDERS
Service/Power Release 3/6/2026 Approved KIRK SANDERS