19409 W FRIAR ST 91335

Certificate Information: 19409 W FRIAR ST 91335

Application / Permit
24016-20000-14149
Plan Check / Job No.
B24VN05878
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO (N) 380 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) WORK PER ENGINEERED DESIGN.
Permit Issued
Issued on 8/22/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/6/2024 OMAR GARNICA
Corrections Issued 5/6/2024 OMAR GARNICA
Issued 8/22/2024 APPLICANT
CofO in Progress 4/25/2025 ALEXANDER HANDY
Permit Finaled 6/5/2025 JOHN JANSON
CofO Issued 6/5/2025 JOHN JANSON
Permit Finaled 6/5/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/8/2024 CARLOS RAMIREZ
Sewer availability Cleared 5/8/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/14/2024 CARLOS RAMIREZ
Construction within easement Cleared 8/9/2024 RIDWAN HARDY

Contact Information

Contractor Remodeling Home Advisors; Lic. No.: 1039580-B 17929 VENTURA BLVD UNIT 5      ENCINO, CA 91316
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/17/2024 Approved ARUTYUN MADATYAN
PLUMBING-Rough 10/17/2024 Partial Approval ARUTYUN MADATYAN
Sewer 10/17/2024 Approved ARUTYUN MADATYAN
Underground Mechanical 10/17/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 11/1/2024 Partial Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 11/1/2024 Partial Approval ARUTYUN MADATYAN
Green Building Rough 11/1/2024 Not Ready for Inspection ARUTYUN MADATYAN
Wood Frame 11/1/2024 Not Ready for Inspection ARUTYUN MADATYAN
ELECTRICAL-Rough 11/22/2024 Approved ALEXANDER HANDY
HVAC-Rough 11/22/2024 Approved ALEXANDER HANDY
Interior/Exterior Lathing 11/22/2024 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 11/22/2024 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 12/12/2024 Approved ALEXANDER HANDY
Green Building Rough 12/12/2024 Approved ALEXANDER HANDY
Insulation 12/12/2024 Approved ALEXANDER HANDY
Wood Frame 12/12/2024 Approved ALEXANDER HANDY
Shower Pan 1/27/2025 Approved KRISTEN CAUSEY
Drywall Nailing 1/29/2025 Approved JUAN ALVARADO
Interior/Exterior Lathing 2/21/2025 Approved SCOTT SOBEL
ELECTRICAL-Final 4/18/2025 Approved ALEXANDER HANDY
Final 4/18/2025 Corrections Issued ALEXANDER HANDY
Green Building Final 4/18/2025 Not Ready for Inspection ALEXANDER HANDY
HVAC-Final 4/18/2025 Approved ALEXANDER HANDY
PLUMBING-Final 4/18/2025 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 4/18/2025 Approved ALEXANDER HANDY
Final 4/25/2025 OK to Issue CofO ALEXANDER HANDY
Green Building Final 4/25/2025 Approved ALEXANDER HANDY