10003 N COLLETT AVE 91343
Certificate Information: 10003 N COLLETT AVE 91343
- Application / Permit
- 24016-20000-14074
- Plan Check / Job No.
- B24VN05855
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Convert (e) detached garage to an ADU per GCS 65852.2 (e)(1)(A)
- Permit Issued
- Issued on 9/9/2024
- Issuing Office
- Current Status
- CofO Issued on 6/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2024 | CAROLEAN BASMA |
| Corrections Issued | 6/11/2024 | CAROLEAN BASMA |
| Plan Check Approved | 7/15/2024 | REZA HAGHIGHAT |
| Issued | 9/9/2024 | APPLICANT |
| CofO in Progress | 4/30/2026 | CHRISTOPHER ROJAS |
| CofO Issued | 6/4/2026 | RUBEN SALAS |
| Permit Finaled | 6/4/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/3/2024 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 7/8/2024 | CHARLES POWELL |
| Address approval | Cleared | 7/9/2024 | GABRIELLA TORRES |
| Roof/Waste drainage to street | Cleared | 7/9/2024 | GABRIELLA TORRES |
| Sewer availability | Cleared | 7/9/2024 | GABRIELLA TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2024 | GABRIELLA TORRES |
Contact Information
| Contractor | Karma Builders Inc; Lic. No.: 878865-B | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: NA93079 | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/20/2024 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/27/2024 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/20/2024 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/20/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 11/20/2024 | Partial Approval | JAVIER RAMOS JR |
| Insulation | 12/10/2024 | No Access for Inspection | JAVIER RAMOS JR |
| Insulation | 12/26/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 1/7/2025 | Partial Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 1/15/2025 | Approved | LOUIS ESCOTO |
| Pre-Inspection | 8/21/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 12/23/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 12/23/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 12/23/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 3/11/2026 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 3/11/2026 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 3/11/2026 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 3/11/2026 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 3/27/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 3/27/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/27/2026 | SGSOV Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/17/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 4/17/2026 | Partial Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/30/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 4/30/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |