5508 W 78TH ST 90045

Certificate Information: 5508 W 78TH ST 90045

Application / Permit
24016-20000-13909
Plan Check / Job No.
B24VN05757
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). WORK DONE PER WFPP. 1 OF 2
Permit Issued
Issued on 9/17/2024
Issuing Office
Metro
Current Status
Issued on 9/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/26/2024 APPLICANT
Assigned to Plan Check Engineer 5/6/2024 MIROOSH KHACHATOORIAN
Corrections Issued 5/6/2024 MIROOSH KHACHATOORIAN
Building Plans Picked Up 5/9/2024 APPLICANT
Plan Check Approved 9/10/2024 ALEC MOUSAKHANIAN
Issued 9/17/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/7/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 5/7/2024 DARIN LAM
Sewer availability Cleared 5/7/2024 DARIN LAM
Specific Plan Cleared 6/18/2024 JOSHUA JONES
Grading Pre-Inspection Cleared 7/18/2024 VASIL MIHALEV
Construction near power lines Cleared 9/4/2024 RIDWAN HARDY

Contact Information

Contractor Cantarero Construction; Lic. No.: 1114527-B 2928 GRAND AVE      HUNTINGTON PARK, CA 90255

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

ELECTRICAL-Rough 6/8/2026   

Inspection Request History

Pre-Inspection 9/29/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 2/20/2026 Corrections Issued HERBERT GIRON
PLUMBING-Rough 2/20/2026 Corrections Issued HERBERT GIRON
Sewer 3/24/2026 Approved JESUS PINEDA
Underground Mechanical 3/24/2026 Partial Approval JESUS PINEDA
Footing/Foundation/Slab 4/1/2026 Not Ready for Inspection ANTHONY EGSON
Footing/Foundation/Slab 4/7/2026 Corrections Issued JESUS PINEDA
PLUMBING-Rough 4/7/2026 Partial Approval JESUS PINEDA