161 1/2 S CITRUS AVE 90036

Certificate Information: 161 1/2 S CITRUS AVE 90036

Application / Permit
24016-20000-13672
Plan Check / Job No.
B24VN05639
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). COMPLY WITH DEPARTMENT ORDER effective date 04/26/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 9/6/2024
Issuing Office
Current Status
CofO Issued on 5/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 JEROME MAGAT PALMA
Corrections Issued 5/4/2024 JEROME MAGAT PALMA
Building Plans Picked Up 5/22/2024 APPLICANT
Issued 9/6/2024 APPLICANT
CofO in Progress 1/23/2026 PETER RUBIO
Permit Finaled 5/11/2026 DANIEL SANCHEZ
CofO Issued 5/11/2026 DANIEL SANCHEZ
Permit Finaled 5/11/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 8/7/2024 WALLIE JONG
Sewer availability Cleared 8/7/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/8/2024 WALLIE JONG
Construction within easement Cleared 8/30/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

PETER RUBIO, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
JOHN TCHANG, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
RYAN TAGUINES, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2024 No Access for Inspection RUBEN PEREZ
Pre-Inspection 10/16/2024 Corrections Issued RUBEN PEREZ
Pre-Inspection 11/12/2024 Partial Inspection RUBEN PEREZ
Underground Mechanical 11/14/2024 Not Ready for Inspection PETER RUBIO
Underground Mechanical 11/18/2024 Approved PETER RUBIO
Excavation/Setback/Form/Re-Bar 12/12/2024 Not Ready for Inspection PETER RUBIO
ELECTRICAL-Rough 6/5/2025 Not Ready for Inspection RUBEN PEREZ
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Not Ready for Inspection RUBEN PEREZ
HVAC-Rough 6/5/2025 Not Ready for Inspection RUBEN PEREZ
PLUMBING-Rough 6/5/2025 Not Ready for Inspection RUBEN PEREZ
ELECTRICAL-Rough 6/25/2025 Approved PETER RUBIO
HVAC-Rough 6/25/2025 Not Ready for Inspection PETER RUBIO
PLUMBING-Rough 6/25/2025 Approved PETER RUBIO
HVAC-Rough 7/30/2025 Approved PETER RUBIO
Interior/Exterior Lathing 7/30/2025 Approved PETER RUBIO
Wood Frame 7/30/2025 Not Ready for Inspection PETER RUBIO
HVAC-Rough 8/22/2025 Approved PETER RUBIO
Insulation 8/22/2025 Approved PETER RUBIO
Interior/Exterior Lathing 8/22/2025 Approved PETER RUBIO
Shower Pan 8/22/2025 Approved PETER RUBIO
Wood Frame 8/22/2025 Approved PETER RUBIO
Drywall Nailing 9/18/2025 Approved PETER RUBIO
BUILDING-Rough-Frame 1/8/2026 Approved PETER RUBIO
Final 1/8/2026 Not Ready for Inspection PETER RUBIO
Green Building Final 1/8/2026 Approved PETER RUBIO
Green Building Rough 1/8/2026 Approved PETER RUBIO
METHANE-Final 1/8/2026 Approved PETER RUBIO
METHANE-Rough 1/8/2026 Approved PETER RUBIO
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved PETER RUBIO
Smoke Detectors 1/8/2026 Approved PETER RUBIO
Final 1/22/2026 OK to Issue CofO PETER RUBIO