18021 W CHATSWORTH ST 91344

Certificate Information: 18021 W CHATSWORTH ST 91344

Application / Permit
24016-20000-13566
Plan Check / Job No.
B24VN05591
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
*EPLAN* CHANGE OF USE FROM RETAIL TO OFFICE [INT. T.I., WORK INCLUDE NEW PARTITION FOR OFFICES, BREAKROOM, TRAINING ROOM AND RESTROOMS, & STRUCTURAL ALTERATION]
Permit Issued
Issued on 7/12/2024
Issuing Office
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 SELLA BENYAMIN
Assigned to Zoning Architect 5/9/2024 AMIR NAKHLA
Corrections Issued 5/15/2024 SEAN SHAHMIRI
Quality Review Completed 5/22/2024 STEVEN KIM
Applicant returned to address corrections 6/28/2024 SELLA BENYAMIN
Plan Check Approved 7/12/2024 SELLA BENYAMIN
Issued 7/12/2024 APPLICANT
CofO in Progress 5/28/2025 DEANDRE HOFFMAN
Permit Finaled 5/29/2025 JEFFREY DURAN
CofO Issued 5/29/2025 JEFFREY DURAN
Permit Finaled 5/29/2025 JEFFREY DURAN

Permit Application Clearance Information

Green Code Cleared 5/22/2024 MICHAEL AYERS
"Q" conditions Cleared 5/23/2024 NATHAN ROMINE
Miscellaneous Cleared 5/23/2024 NATHAN ROMINE
Miscellaneous Cleared 5/23/2024 NATHAN ROMINE
ZA Case Cleared 5/23/2024 NATHAN ROMINE
ZI Cleared 5/23/2024 NATHAN ROMINE
Address approval Cleared 6/1/2024 CARLOS AGUILERA
Sewer availability Cleared 6/1/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/3/2024 CARLOS AGUILERA
Specific Plan Cleared 6/4/2024 OLGA AYALA
DAS Clearance Cleared 6/6/2024 Khuong Truong
Zoning Plan Check Cleared 7/2/2024 Khuong Truong

Contact Information

Architect Cataldo,, John G; Lic. No.: C10457 835 MISSION STREET      SOUTH PASADENA, CA 91030
Contractor Advanced Contractors Inc; Lic. No.: 382163-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/30/2024 Partial Inspection DEANDRE HOFFMAN
Wood Frame 11/22/2024 Approved DEANDRE HOFFMAN
Light Gage Steel Frame 12/17/2024 Partial Inspection DEANDRE HOFFMAN
Insulation 1/9/2025 No Access for Inspection DEANDRE HOFFMAN
Insulation 1/14/2025 Approved DEANDRE HOFFMAN
Drywall Nailing 1/22/2025 Approved DEANDRE HOFFMAN
Partition/T-Bar Ceiling 2/21/2025 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 4/21/2025 Partial Inspection DEANDRE HOFFMAN
Final 5/21/2025 Partial Inspection DEANDRE HOFFMAN
Green Building Final 5/21/2025 Approved DEANDRE HOFFMAN
Green Building Rough 5/21/2025 Approved DEANDRE HOFFMAN
Reinforced Masonry Frame 5/21/2025 Approved DEANDRE HOFFMAN
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved DEANDRE HOFFMAN
Smoke Detectors 5/21/2025 Approved DEANDRE HOFFMAN
Final 5/28/2025 OK to Issue CofO DEANDRE HOFFMAN