11487 W CALVERT ST 91606
Certificate Information: 11487 W CALVERT ST 91606
- Application / Permit
- 24016-20000-13524
- Plan Check / Job No.
- B24VN05570
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE AND PLAYROOM INTO A 11'-6" X 18'-1" STORAGE AND 23'-11" X 18'-1" ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER ENGINEER
- Permit Issued
- Issued on 11/23/2024
- Issuing Office
- Current Status
- CofO Issued on 12/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 4/29/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 5/23/2024 | DANIEL ABRAMYAN |
| Applicant returned to address corrections | 10/7/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 10/20/2024 | DANIEL ABRAMYAN |
| Issued | 11/23/2024 | APPLICANT |
| CofO in Progress | 11/22/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| Permit Finaled | 12/26/2025 | RUBEN SALAS |
| CofO Issued | 12/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/4/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 10/4/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Almalla,, Dean; Lic. No.: NA58024 | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/29/2025 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 5/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 5/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 5/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 5/6/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 5/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 5/6/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Sewer | 5/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 5/6/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 6/11/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 6/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 6/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 7/2/2025 | Partial Approval | MICHAEL CORTEZ |
| HVAC-Rough | 7/7/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/11/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/11/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 7/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 7/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 7/14/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 7/15/2025 | Conditional Approval | JUAN VALENZUELA |
| Drywall Nailing | 7/21/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 7/29/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 9/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 9/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Final | 9/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Final | 9/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/26/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 9/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 10/16/2025 | Not Ready for Inspection | JOSE AVILA |
| PLUMBING-Final | 10/16/2025 | Approved | JOSE AVILA |
| Final | 10/27/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 10/27/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Final | 11/18/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 11/18/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |