7957-7959 N BEEMAN AVE 91605
Certificate Information: 7957-7959 N BEEMAN AVE 91605
- Application / Permit
- 24016-20000-13008
- Plan Check / Job No.
- B24VN05291
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). REMODEL (E) BATHROOM IN (E) SFD.
- Permit Issued
- Issued on 5/21/2024
- Issuing Office
- Current Status
- CofO Issued on 9/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/24/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 4/27/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/16/2024 | APPLICANT |
| Applicant returned to address corrections | 5/20/2024 | ANGELICA DAVE |
| Plan Check Approved | 5/21/2024 | HAYATO TSUCHIYA |
| Issued | 5/21/2024 | APPLICANT |
| CofO in Progress | 9/3/2024 | VINCENT HANLEY |
| CofO in Progress | 9/3/2024 | VINCENT HANLEY |
| CofO Issued | 9/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/4/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/28/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/28/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 5/28/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/30/2024 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/30/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 5/30/2024 | Partial Approval | GREGG CUMMINGS |
| Wood Frame | 6/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/18/2024 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/18/2024 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 6/18/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 6/18/2024 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/27/2024 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/27/2024 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/27/2024 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/27/2024 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 6/27/2024 | Approved | GREGG CUMMINGS |
| Insulation | 7/2/2024 | Approved | GREGG CUMMINGS |
| Wood Frame | 7/2/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/9/2024 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 7/9/2024 | Approved | GREGG CUMMINGS |
| Green Building Rough | 7/9/2024 | Approved | GREGG CUMMINGS |
| MERV13>=Rough | 7/9/2024 | Approved | GREGG CUMMINGS |
| Shower Pan | 8/2/2024 | Corrections Issued | LOUIS ESCOTO |
| Interior/Exterior Lathing | 8/6/2024 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 8/7/2024 | Approved | GREGG CUMMINGS |
| Final | 8/21/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 8/21/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| MERV13>=Final | 8/21/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/21/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 8/21/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/28/2024 | Approved | VINCENT HANLEY |
| Final | 8/28/2024 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 8/28/2024 | Approved | VINCENT HANLEY |
| HVAC-Final | 8/28/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 8/28/2024 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/28/2024 | SGSOV Not Required | VINCENT HANLEY |
| Service/Power Release | 8/28/2024 | Approved | VINCENT HANLEY |
| Final | 9/3/2024 | OK to Issue CofO | VINCENT HANLEY |