9437 N MONOGRAM AVE 91343
Certificate Information: 9437 N MONOGRAM AVE 91343
- Application / Permit
- 24016-20000-12606
- Plan Check / Job No.
- B24VN05124
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER WFPP
- Permit Issued
- Issued on 8/22/2024
- Issuing Office
- Current Status
- CofO Issued on 8/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 4/23/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/25/2024 | APPLICANT |
| Issued | 8/22/2024 | APPLICANT |
| CofO in Progress | 7/24/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
| CofO Issued | 8/5/2025 | RUBEN SALAS |
| Permit Finaled | 8/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/25/2024 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 4/29/2024 | CHARLES POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/19/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/25/2024 | Partial Approval | SALVADOR MARTINEZ |
| Sewer | 9/25/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 10/2/2024 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 10/2/2024 | Approved | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 10/8/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 10/11/2024 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 10/11/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Partial Inspection | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 10/31/2024 | No Access for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/6/2024 | Partial Approval | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/12/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Excavation/Setback/Form/Re-Bar | 11/19/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Deputy Drilled-In Anchors | 11/22/2024 | Conditional Approval | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 11/22/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 1/16/2025 | Approved | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2025 | Partial Approval | SALVADOR MARTINEZ |
| HVAC-Rough | 1/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 1/16/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/23/2025 | Partial Approval | SALVADOR MARTINEZ |
| Green Building Rough | 1/23/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 1/23/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/23/2025 | Partial Approval | SALVADOR MARTINEZ |
| Insulation | 2/4/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/11/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 2/19/2025 | Approved | SALVADOR MARTINEZ |
| Shower Pan | 2/19/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 3/19/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 6/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 6/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Gas Test | 6/26/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 6/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 6/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Final | 7/10/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Green Building Final | 7/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Final | 7/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| PLUMBING-Final | 7/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| SGSOV-Seismic Gas S/O Valve | 7/10/2025 | SGSOV Approved | NICHOLAS TROWBRIDGE |
| Smoke Detectors | 7/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Final | 7/21/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/21/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 7/21/2025 | Approved | JENNIFER RABUCHIN |