10937 N LOUISE AVE 91344
Certificate Information: 10937 N LOUISE AVE 91344
- Application / Permit
- 24016-20000-12551
- Plan Check / Job No.
- B24VN05089
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO (N) JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22. ALL WORK PER WFPP.
- Permit Issued
- Issued on 4/29/2024
- Issuing Office
- Current Status
- CofO Corrected on 9/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 4/23/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/24/2024 | APPLICANT |
| Issued | 4/29/2024 | APPLICANT |
| CofO in Progress | 4/8/2025 | STEVEN BACK |
| CofO Issued-Status Void | 4/11/2025 | JOHN JANSON |
| Permit Finaled-Status Void | 4/11/2025 | JOHN JANSON |
| Re-Activate Permit | 9/2/2025 | JOHN JANSON |
| Permit Finaled | 9/2/2025 | JOHN JANSON |
| CofO Corrected | 9/2/2025 | JOHN JANSON |
| Permit Finaled | 9/2/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/25/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/17/2024 | Conditional Approval | STEVEN BACK |
| Footing/Foundation/Slab | 6/21/2024 | Approved | STEVEN BACK |
| Special/Order Compliance | 6/21/2024 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 7/11/2024 | Approved | JEFFREY BULL |
| HVAC-Rough | 8/2/2024 | No Access for Inspection | KRISTEN CAUSEY |
| PLUMBING-Rough | 8/2/2024 | No Access for Inspection | KRISTEN CAUSEY |
| HVAC-Rough | 8/7/2024 | Approved | STEVEN BACK |
| PLUMBING-Rough | 8/7/2024 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 8/15/2024 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 9/5/2024 | Partial Approval | DAVID SCANTLIN |
| Sewer | 9/5/2024 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 9/17/2024 | Approved | STEVEN BACK |
| PLUMBING-Rough | 9/17/2024 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Corrections Issued | SCOTT SOBEL |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 11/18/2024 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 1/9/2025 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/9/2025 | Not Ready for Inspection | STEVEN BACK |
| Green Building Rough | 1/9/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 1/16/2025 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 1/16/2025 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 1/23/2025 | Approved | STEVEN BACK |
| Green Building Rough | 1/23/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 1/23/2025 | Partial Approval | STEVEN BACK |
| Insulation | 1/28/2025 | Approved | STEVEN BACK |
| Drywall Nailing | 2/4/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/11/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 4/2/2025 | Approved | STEVEN BACK |
| Final | 4/2/2025 | Corrections Issued | STEVEN BACK |
| Green Building Final | 4/2/2025 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Final | 4/2/2025 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Final | 4/2/2025 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Gas Company | STEVEN BACK |
| Smoke Detectors | 4/2/2025 | Approved | STEVEN BACK |
| Final | 4/8/2025 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 4/8/2025 | Approved | STEVEN BACK |