7143-7145 N DARNOCH WAY 91307

Certificate Information: 7143-7145 N DARNOCH WAY 91307

Application / Permit
24016-20000-12170
Plan Check / Job No.
B24VN04929
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan: Convert Existing Attached Garage to Junior Accessory Dwelling Unit (JADU 453.2SQFT) PER STATE LAW
Permit Issued
Issued on 5/8/2024
Issuing Office
Current Status
CofO Issued on 12/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2024 APPLICANT
Assigned to Plan Check Engineer 4/17/2024 KHUONG TRUONG
Corrections Issued 4/18/2024 KHUONG TRUONG
Plan Check Approved 4/27/2024 KHUONG TRUONG
Issued 5/8/2024 APPLICANT
CofO in Progress 12/17/2025 JEFFREY HARTLINE
Permit Finaled 12/17/2025 JOHN JANSON
CofO Issued 12/17/2025 JOHN JANSON
Permit Finaled 12/17/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/19/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/19/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/24/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 4/24/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Sufipur,, Rambod; Lic. No.: C90761 13 MEADOWBROOK      ALISO VIEJO, CA 92656

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 5/16/2024 Corrections Issued JEFFREY HARTLINE
Underground Mechanical 5/16/2024 Approved JEFFREY HARTLINE
Deputy Drilled-In Anchors 5/28/2024 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 5/29/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 6/5/2024 Approved JEFFREY HARTLINE
Gas Test 6/5/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 6/5/2024 Approved JEFFREY HARTLINE
Special/Order Compliance 6/13/2024 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Insulation 6/20/2024 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Partial Approval JEFFREY HARTLINE
HVAC-Rough 9/16/2024 Approved JEFFREY HARTLINE
Wood Frame 10/7/2024 No Access for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/10/2024 Approved JEFFREY HARTLINE
Green Building Rough 10/10/2024 Approved JEFFREY HARTLINE
HVAC-Rough 10/10/2024 Approved JEFFREY HARTLINE
Insulation 10/10/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 10/10/2024 Partial Approval JEFFREY HARTLINE
Drywall Nailing 10/21/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 12/6/2024 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 2/26/2025 Approved JEFFREY HARTLINE
Final 2/26/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 2/26/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 2/26/2025 Approved JEFFREY HARTLINE
Special/Order Compliance 3/14/2025 Corrections Issued JEFFREY HARTLINE
Final 5/22/2025 Corrections Issued JEFFREY HARTLINE
Special/Order Compliance 11/21/2025 Corrections Issued JEFFREY HARTLINE
HVAC-Final 12/8/2025 No Access for Inspection JEFFREY HARTLINE
HVAC-Final 12/9/2025 No Access for Inspection JEFFREY HARTLINE
Final 12/16/2025 OK to Issue CofO JEFFREY HARTLINE
Green Building Final 12/16/2025 Approved JEFFREY HARTLINE
HVAC-Final 12/16/2025 Approved JEFFREY HARTLINE
Special/Order Compliance 12/16/2025 Partial Inspection HENRY KIM