11742 1/2 W STRATHERN ST 91605
Certificate Information: 11742 1/2 W STRATHERN ST 91605
- Application / Permit
- 24016-20000-12086
- Plan Check / Job No.
- B24VN04893
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert existing garage and storage to ADU per GCS 65852.2(e)(1)(A) "COMPLY WITH DEPARTMENT ORDER effective date 03/29/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" CEIS Case Number is 998859.
- Permit Issued
- Issued on 7/16/2024
- Issuing Office
- Current Status
- CofO Issued on 6/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/11/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/16/2024 | NGHI SU |
| Corrections Issued | 4/17/2024 | NGHI SU |
| Plan Check Approved | 6/25/2024 | NGHI SU |
| Issued | 7/16/2024 | APPLICANT |
| CofO in Progress | 2/6/2025 | LEO MILBAUER |
| Permit Finaled | 6/11/2025 | DAVID JAMES |
| CofO Issued | 6/11/2025 | DAVID JAMES |
| Permit Finaled | 6/11/2025 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/22/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/22/2024 | LEE GUILBEAUX |
| Hold | Cleared | 7/26/2024 | ALEXIS SCHULTZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/25/2024 | Conditional Approval | LEO MILBAUER |
| Footing/Foundation/Slab | 7/26/2024 | Approved | LEO MILBAUER |
| BUILDING-Rough-Frame | 10/10/2024 | Not Ready for Inspection | LEO MILBAUER |
| Excavation/Setback/Form/Re-Bar | 10/10/2024 | Approved | LEO MILBAUER |
| Interior/Exterior Lathing | 10/10/2024 | Not Ready for Inspection | LEO MILBAUER |
| BUILDING-Rough-Frame | 10/24/2024 | Partial Inspection | LEO MILBAUER |
| Deputy Drilled-In Anchors | 10/24/2024 | Approved | LEO MILBAUER |
| ELECTRICAL-Rough | 10/24/2024 | Partial Inspection | LEO MILBAUER |
| HVAC-Rough | 10/24/2024 | Partial Inspection | LEO MILBAUER |
| PLUMBING-Rough | 10/24/2024 | Approved | LEO MILBAUER |
| BUILDING-Rough-Frame | 10/31/2024 | Approved | LEO MILBAUER |
| ELECTRICAL-Rough | 10/31/2024 | Partial Inspection | LEO MILBAUER |
| HVAC-Rough | 10/31/2024 | Partial Approval | LEO MILBAUER |
| Interior/Exterior Lathing | 10/31/2024 | Not Ready for Inspection | LEO MILBAUER |
| PLUMBING-Rough | 10/31/2024 | Approved | LEO MILBAUER |
| ELECTRICAL-Rough | 11/6/2024 | Corrections Issued | LEO MILBAUER |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2024 | Corrections Issued | LEO MILBAUER |
| Interior/Exterior Lathing | 11/6/2024 | Corrections Issued | LEO MILBAUER |
| PLUMBING-Rough | 11/6/2024 | Corrections Issued | LEO MILBAUER |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2024 | Partial Inspection | LEO MILBAUER |
| Interior/Exterior Lathing | 11/13/2024 | Partial Inspection | LEO MILBAUER |
| Insulation | 11/21/2024 | Approved | LEO MILBAUER |
| Interior/Exterior Lathing | 11/21/2024 | Not Ready for Inspection | LEO MILBAUER |
| Drywall Nailing | 11/26/2024 | Approved | LEO MILBAUER |
| Interior/Exterior Lathing | 11/26/2024 | Approved | LEO MILBAUER |
| Final | 12/30/2024 | Corrections Issued | LEO MILBAUER |
| Green Building Final | 12/31/2024 | Approved | LEO MILBAUER |
| SGSOV-Seismic Gas S/O Valve | 12/31/2024 | SGSOV Approved | LEO MILBAUER |
| Smoke Detectors | 12/31/2024 | Approved | LEO MILBAUER |
| ELECTRICAL-Final | 1/16/2025 | Partial Inspection | LEO MILBAUER |
| Final | 1/16/2025 | Not Ready for Inspection | LEO MILBAUER |
| Service/Power Release | 1/16/2025 | Partial Inspection | LEO MILBAUER |
| Final | 1/30/2025 | Not Ready for Inspection | LEO MILBAUER |
| Service/Power Release | 1/30/2025 | Conditional Approval | LEO MILBAUER |
| Final | 2/5/2025 | Conditional Approval | LEO MILBAUER |