11742 1/2 W STRATHERN ST 91605

Certificate Information: 11742 1/2 W STRATHERN ST 91605

Application / Permit
24016-20000-12086
Plan Check / Job No.
B24VN04893
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Convert existing garage and storage to ADU per GCS 65852.2(e)(1)(A) "COMPLY WITH DEPARTMENT ORDER effective date 03/29/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" CEIS Case Number is 998859.
Permit Issued
Issued on 7/16/2024
Issuing Office
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/16/2024 NGHI SU
Corrections Issued 4/17/2024 NGHI SU
Plan Check Approved 6/25/2024 NGHI SU
Issued 7/16/2024 APPLICANT
CofO in Progress 2/6/2025 LEO MILBAUER
Permit Finaled 6/11/2025 DAVID JAMES
CofO Issued 6/11/2025 DAVID JAMES
Permit Finaled 6/11/2025 DAVID JAMES

Permit Application Clearance Information

Address approval Cleared 4/22/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/22/2024 LEE GUILBEAUX
Sewer availability Cleared 4/22/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/22/2024 LEE GUILBEAUX
Hold Cleared 7/26/2024 ALEXIS SCHULTZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RICHARD ROBLES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
FELIPE PENICHE, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/25/2024 Conditional Approval LEO MILBAUER
Footing/Foundation/Slab 7/26/2024 Approved LEO MILBAUER
BUILDING-Rough-Frame 10/10/2024 Not Ready for Inspection LEO MILBAUER
Excavation/Setback/Form/Re-Bar 10/10/2024 Approved LEO MILBAUER
Interior/Exterior Lathing 10/10/2024 Not Ready for Inspection LEO MILBAUER
BUILDING-Rough-Frame 10/24/2024 Partial Inspection LEO MILBAUER
Deputy Drilled-In Anchors 10/24/2024 Approved LEO MILBAUER
ELECTRICAL-Rough 10/24/2024 Partial Inspection LEO MILBAUER
HVAC-Rough 10/24/2024 Partial Inspection LEO MILBAUER
PLUMBING-Rough 10/24/2024 Approved LEO MILBAUER
BUILDING-Rough-Frame 10/31/2024 Approved LEO MILBAUER
ELECTRICAL-Rough 10/31/2024 Partial Inspection LEO MILBAUER
HVAC-Rough 10/31/2024 Partial Approval LEO MILBAUER
Interior/Exterior Lathing 10/31/2024 Not Ready for Inspection LEO MILBAUER
PLUMBING-Rough 10/31/2024 Approved LEO MILBAUER
ELECTRICAL-Rough 11/6/2024 Corrections Issued LEO MILBAUER
Floor/Roof Diaphrgm/Shear Wall 11/6/2024 Corrections Issued LEO MILBAUER
Interior/Exterior Lathing 11/6/2024 Corrections Issued LEO MILBAUER
PLUMBING-Rough 11/6/2024 Corrections Issued LEO MILBAUER
Floor/Roof Diaphrgm/Shear Wall 11/13/2024 Partial Inspection LEO MILBAUER
Interior/Exterior Lathing 11/13/2024 Partial Inspection LEO MILBAUER
Insulation 11/21/2024 Approved LEO MILBAUER
Interior/Exterior Lathing 11/21/2024 Not Ready for Inspection LEO MILBAUER
Drywall Nailing 11/26/2024 Approved LEO MILBAUER
Interior/Exterior Lathing 11/26/2024 Approved LEO MILBAUER
Final 12/30/2024 Corrections Issued LEO MILBAUER
Green Building Final 12/31/2024 Approved LEO MILBAUER
SGSOV-Seismic Gas S/O Valve 12/31/2024 SGSOV Approved LEO MILBAUER
Smoke Detectors 12/31/2024 Approved LEO MILBAUER
ELECTRICAL-Final 1/16/2025 Partial Inspection LEO MILBAUER
Final 1/16/2025 Not Ready for Inspection LEO MILBAUER
Service/Power Release 1/16/2025 Partial Inspection LEO MILBAUER
Final 1/30/2025 Not Ready for Inspection LEO MILBAUER
Service/Power Release 1/30/2025 Conditional Approval LEO MILBAUER
Final 2/5/2025 Conditional Approval LEO MILBAUER