4429 N FARMDALE AVE 91602
Certificate Information: 4429 N FARMDALE AVE 91602
- Application / Permit
- 24016-20000-11952
- Plan Check / Job No.
- B24VN04828
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) - PER ENGINEER
- Permit Issued
- Issued on 8/16/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 4/17/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/18/2024 | APPLICANT |
| Issued | 8/16/2024 | APPLICANT |
| CofO in Progress | 5/20/2025 | JUAN VALENZUELA |
| Permit Finaled | 5/21/2025 | RUBEN SALAS |
| CofO Issued | 5/21/2025 | RUBEN SALAS |
| Permit Finaled | 5/21/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/22/2024 | CARLOS AGUILERA |
| ZI | Cleared | 5/7/2024 | BRENNEN OBETO |
| Construction near power lines | Cleared | 8/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | J'S Vision Construction Inc; Lic. No.: 1043336-B | 14340 VENTURA BLVD SHERMAN OAKS, CA 91423 |
| Engineer | Crook,, Barrett Cameron; Lic. No.: C57196 | 5306 MULHOLLAND DRIVE SUMMERVILLE, SC 29485 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/19/2024 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 8/19/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/10/2024 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 9/10/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 9/17/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 9/17/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 9/23/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/23/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 9/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/23/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 10/1/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 10/1/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/4/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 10/4/2024 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 10/8/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 10/8/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 10/8/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 10/21/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 10/21/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Final | 1/27/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 1/27/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/27/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 1/31/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/31/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/31/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 2/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Special/Order Compliance | 2/4/2025 | Corrections Issued | JUAN VALENZUELA |
| Final | 2/18/2025 | Partial Approval | JUAN VALENZUELA |
| Green Building Final | 2/18/2025 | Approved | JUAN VALENZUELA |
| Smoke Detectors | 2/18/2025 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 5/16/2025 | Approved | JUAN VALENZUELA |
| Final | 5/16/2025 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 5/16/2025 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 5/16/2025 | Approved | JUAN VALENZUELA |