20404 W LONDELIUS ST 91306

Certificate Information: 20404 W LONDELIUS ST 91306

Application / Permit
24016-20000-11912
Plan Check / Job No.
B24VN04793
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 5/23/2024
Issuing Office
Current Status
CofO Issued on 12/1/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/15/2024 GIOVANNY CHAVEZ
Corrections Issued 4/16/2024 GIOVANNY CHAVEZ
Applicant returned to address corrections 5/2/2024 ISIS ARGUETA
Plan Check Approved 5/3/2024 ISIS ARGUETA
Issued 5/23/2024 APPLICANT
CofO in Progress 11/21/2025 JEFFREY HARTLINE
Permit Finaled 12/1/2025 JOHN JANSON
CofO Issued 12/1/2025 JOHN JANSON
Permit Finaled 12/1/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/18/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/18/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/24/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/19/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/8/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 10/8/2024 Partial Approval JEFFREY HARTLINE
Sewer 10/8/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 10/25/2024 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/25/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 10/25/2024 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 10/25/2024 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 10/25/2024 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/31/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval JEFFREY HARTLINE
HVAC-Rough 10/31/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 10/31/2024 Approved JEFFREY HARTLINE
BUILDING-Rough-Frame 11/25/2024 Partial Approval JEFFREY HARTLINE
Green Building Rough 11/25/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 11/25/2024 Partial Approval JEFFREY HARTLINE
Special/Order Compliance 11/25/2024 Corrections Issued JEFFREY HARTLINE
Insulation 12/11/2024 Approved JEFFREY HARTLINE
Insulation 12/26/2024 Approved JEFFREY HARTLINE
Drywall Nailing 12/31/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 12/31/2024 Partial Approval JEFFREY HARTLINE
Final 7/16/2025 Corrections Issued JEFFREY HARTLINE
BUILDING-Rough-Frame 8/26/2025 Approved JEFFREY HARTLINE
Final 8/26/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 8/26/2025 Not Ready for Inspection JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 8/26/2025 Approved JEFFREY HARTLINE
Final 10/20/2025 Corrections Issued JEFFREY HARTLINE
Green Building Final 10/20/2025 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 10/20/2025 SGSOV Approved JEFFREY HARTLINE
ELECTRICAL-Final 11/17/2025 Approved JEFFREY HARTLINE
Final 11/17/2025 OK to Issue CofO JEFFREY HARTLINE
HVAC-Final 11/17/2025 Approved JEFFREY HARTLINE
PLUMBING-Final 11/17/2025 Approved JEFFREY HARTLINE
Service/Power Release 11/17/2025 Approved JEFFREY HARTLINE