7552-7554 N BELMAR AVE 91335

Certificate Information: 7552-7554 N BELMAR AVE 91335

Application / Permit
24016-20000-11794
Plan Check / Job No.
B24VN04752
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) ATTACHED GARAGE TO (N) 403 SF JADU PER GCS 65852.2(e)(1)(A) AND 65852.22. ALL WORK PER ENGINEERING
Permit Issued
Issued on 5/9/2024
Issuing Office
Current Status
CofO Issued on 2/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/15/2024 LUISANGEL VALENZUELA
Corrections Issued 4/16/2024 LUISANGEL VALENZUELA
Plan Check Approved 5/8/2024 LUISANGEL VALENZUELA
Issued 5/9/2024 APPLICANT
CofO in Progress 1/31/2025 ARUTYUN MADATYAN
Permit Finaled 2/5/2025 JOHN JANSON
CofO Issued 2/5/2025 JOHN JANSON
Permit Finaled 2/5/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/4/2024 CARLOS AGUILERA
Sewer availability Cleared 5/4/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/22/2024 Corrections Issued JEFFREY BULL
PLUMBING-Rough 7/22/2024 Partial Approval JEFFREY BULL
Deputy Drilled-In Anchors 7/23/2024 Conditional Approval JEFFREY BULL
Footing/Foundation/Slab 8/8/2024 Approved JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 8/30/2024 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 8/30/2024 Approved JEFFREY BULL
Insulation 9/12/2024 Approved SCOTT SOBEL
Interior/Exterior Lathing 9/12/2024 Partial Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 9/20/2024 Approved JEFFREY BULL
Shower Pan 9/20/2024 Not Ready for Inspection JEFFREY BULL
Drywall Nailing 10/3/2024 Approved JEFFREY BULL
Green Building Rough 10/3/2024 Approved JEFFREY BULL
Interior/Exterior Lathing 10/25/2024 Approved MORRIS JACKSON
ELECTRICAL-Final 12/9/2024 Not Ready for Inspection ARUTYUN MADATYAN
Gas Test 12/9/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 12/9/2024 Not Ready for Inspection ARUTYUN MADATYAN
Sewer 12/9/2024 Approved ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 1/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
Green Building Final 1/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 1/16/2025 Not Ready for Inspection ARUTYUN MADATYAN
BUILDING-Rough-Frame 1/23/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 1/23/2025 Not Ready for Inspection ARUTYUN MADATYAN
Final 1/23/2025 Corrections Issued ARUTYUN MADATYAN
Green Building Final 1/23/2025 Approved ARUTYUN MADATYAN
HVAC-Final 1/23/2025 Not Ready for Inspection ARUTYUN MADATYAN
PLUMBING-Final 1/23/2025 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved ARUTYUN MADATYAN
Smoke Detectors 1/23/2025 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 1/30/2025 Approved ARUTYUN MADATYAN
Final 1/30/2025 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 1/30/2025 Approved ARUTYUN MADATYAN
PLUMBING-Final 1/30/2025 Approved ARUTYUN MADATYAN
Service/Power Release 1/30/2025 Approved ARUTYUN MADATYAN