20407-20411 W STRATHERN ST 91306
Certificate Information: 20407-20411 W STRATHERN ST 91306
- Application / Permit
- 24016-20000-11291
- Plan Check / Job No.
- B24VN04518
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Convert (32' x 24' Irregular Shape) portion of existing garage to an Accessory Dwelling Unit per LAMC 12.22 A.33 (c) and (e). Convert remaining (24' x 11') portion of garage to storage. Convert (24' x 17') Second Story Rec Room with (24' x 15'-2") Addition into a Dwelling Unit per SB9 Two-Unit Development CA Govt Code 65852.21.
- Permit Issued
- Issued on 10/9/2024
- Issuing Office
- Current Status
- CofO Issued on 2/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 4/16/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 4/17/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/19/2024 | APPLICANT |
| Applicant returned to address corrections | 7/9/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 9/27/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 10/9/2024 | VAHAN JIVALAGIAN |
| Issued | 10/9/2024 | APPLICANT |
| CofO in Progress | 12/8/2025 | ALEXANDER HANDY |
| Permit Finaled | 2/28/2026 | MICHAEL PELHAM |
| CofO Issued | 2/28/2026 | MICHAEL PELHAM |
| Permit Finaled | 2/28/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 5/2/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | CARLOS RAMIREZ |
| "T" removal | Cleared | 5/31/2024 | DORIAN AGUILAR |
| Senate Bill 9 | Cleared | 6/3/2024 | ALEX VELA |
| Roof/Waste drainage to street | Cleared | 9/27/2024 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/22/2024 | Partial Inspection | ALEXANDER HANDY |
| Deputy Drilled-In Anchors | 12/6/2024 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 12/11/2024 | Not Ready for Inspection | TROY SANDERS |
| Footing/Foundation/Slab | 1/6/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | SEAN WIRCH |
| Sewer | 3/4/2025 | Approved | SEAN WIRCH |
| HVAC-Rough | 4/10/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Rough | 5/5/2025 | Approved | ALEXANDER HANDY |
| Gas Test | 5/5/2025 | Partial Approval | ALEXANDER HANDY |
| HVAC-Rough | 5/5/2025 | Corrections Issued | ALEXANDER HANDY |
| PLUMBING-Rough | 5/5/2025 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/8/2025 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 5/8/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| HVAC-Rough | 5/8/2025 | Conditional Approval | ALEXANDER HANDY |
| Insulation | 5/19/2025 | Approved | ALEXANDER HANDY |
| Shower Pan | 5/19/2025 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 5/27/2025 | Approved | SCOTT SOBEL |
| Green Building Rough | 5/27/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 5/27/2025 | Partial Approval | SCOTT SOBEL |
| Interior/Exterior Lathing | 6/18/2025 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 6/18/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/13/2025 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/15/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Green Building Final | 10/15/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 10/15/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/20/2025 | Approved | ALEXANDER HANDY |
| Final | 10/20/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 10/20/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 10/20/2025 | SGSOV Not Ready | ALEXANDER HANDY |
| Smoke Detectors | 10/20/2025 | Approved | ALEXANDER HANDY |
| Final | 11/12/2025 | Partial Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 11/12/2025 | SGSOV Approved | ROBERT GOLD |
| ELECTRICAL-Final | 11/24/2025 | Corrections Issued | HENRY KIM |
| Final | 11/24/2025 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 12/1/2025 | Approved | ALEXANDER HANDY |
| Final | 12/1/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 12/1/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 12/1/2025 | Approved | ALEXANDER HANDY |