19747 W SATICOY ST 91306
Certificate Information: 19747 W SATICOY ST 91306
- Application / Permit
- 24016-20000-11146
- Plan Check / Job No.
- B24VN04448
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Detached Garage Conversion to ADU per GCS 65852.2(e)(1)(A). All Work Done per WFPP
- Permit Issued
- Issued on 6/4/2024
- Issuing Office
- Current Status
- CofO Issued on 9/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/8/2024 | DAVID CASTILLO |
| Corrections Issued | 4/9/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/22/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/9/2024 | CAROLEAN BASMA |
| Plan Check Approved | 6/4/2024 | CAROLEAN BASMA |
| Issued | 6/4/2024 | APPLICANT |
| CofO in Progress | 9/18/2024 | ARUTYUN MADATYAN |
| Permit Finaled | 9/25/2024 | JOHN JANSON |
| CofO Issued | 9/25/2024 | JOHN JANSON |
| Permit Finaled | 9/25/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 4/15/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 4/15/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/2/2024 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 7/2/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/16/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | ARUTYUN MADATYAN |
| Gas Test | 7/16/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 7/16/2024 | Approved | ARUTYUN MADATYAN |
| Sewer | 7/16/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 7/22/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/22/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 7/22/2024 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 7/22/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/22/2024 | Partial Approval | ARUTYUN MADATYAN |
| Insulation | 7/24/2024 | Conditional Approval | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 7/29/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 7/29/2024 | Partial Inspection | ARUTYUN MADATYAN |
| Shower Pan | 7/29/2024 | Approved | ARUTYUN MADATYAN |
| Final | 9/3/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 9/3/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 9/3/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 9/3/2024 | Approved | ARUTYUN MADATYAN |
| Final | 9/9/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Green Building Final | 9/9/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 9/17/2024 | Approved | ARUTYUN MADATYAN |
| Final | 9/17/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 9/17/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 9/17/2024 | Approved | ARUTYUN MADATYAN |