8517 N SHIRLEY AVE 91324

Certificate Information: 8517 N SHIRLEY AVE 91324

Application / Permit
24016-20000-11013
Plan Check / Job No.
B24VN04365
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE TO REMOVE AND REBUILD GARAGE INCLUDING FOUNDATION UNDERPIN, REMOVE AND REPLACE EXISTING WINDOWS AND DOORS THROUGHOUT. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 6/10/2024
Issuing Office
Valley
Current Status
Permit Finaled on 5/29/2026

Permit Application Status History

Submitted 4/3/2024 APPLICANT
Assigned to Plan Check Engineer 4/9/2024 MADISON ODELL
Corrections Issued 4/9/2024 MADISON ODELL
Building Plans Picked Up 4/16/2024 APPLICANT
Plan Check Approved 4/19/2024 YAQUB MIRZA
Issued 6/10/2024 APPLICANT
Permit Finaled 5/28/2026 JEFFREY HARTLINE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Sandoval,, Martin; Lic. No.: C56905 12761 DAIRY ST      EASTVALE, CA 92880

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2024 Approved CHRIS CHRISTENSEN
Special/Order Compliance 6/24/2024 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 7/10/2024 Corrections Issued CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/2/2024 Corrections Issued CHRIS CHRISTENSEN
Footing/Foundation/Slab 12/11/2024 Conditional Approval CHRIS CHRISTENSEN
Wood Frame 7/2/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/31/2025 Partial Approval JEFFREY HARTLINE
ELECTRICAL-Rough 8/27/2025 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 8/27/2025 Approved CHRIS CHRISTENSEN
Pre-Inspection 10/15/2025 Approved CHRIS CHRISTENSEN
Wood Frame 10/15/2025 Partial Approval CHRIS CHRISTENSEN
Wood Frame 11/10/2025 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/17/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 11/17/2025 Approved JEFFREY HARTLINE
Green Building Rough 11/17/2025 Approved JEFFREY HARTLINE
HVAC-Rough 11/17/2025 Approved JEFFREY HARTLINE
Insulation 11/24/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 11/24/2025 Partial Approval JEFFREY HARTLINE
Drywall Nailing 12/3/2025 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 12/10/2025 Approved JEFFREY HARTLINE
Shower Pan 12/10/2025 Approved JEFFREY HARTLINE
Final 4/30/2026 Corrections Issued JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 4/30/2026 SGSOV Not Ready JEFFREY HARTLINE
Smoke Detectors 4/30/2026 Approved JEFFREY HARTLINE
Final 5/28/2026 Permit Finaled JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 5/28/2026 SGSOV Approved JEFFREY HARTLINE
Service/Power Release 5/28/2026 Approved JEFFREY HARTLINE