13003 W VICTORY BLVD 91606

Certificate Information: 13003 W VICTORY BLVD 91606

Application / Permit
24016-20000-10922
Plan Check / Job No.
B24VN04331
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Bank
Work Description
<ePLAN> TENANT IMPROVEMENT TO (E) BANK LOCATION INCLUDING, SEISMIC UPGRADE, UPDATED ROOF, STOREFRONT ENTRY MODIFICATION, AND ACCESSIBILITY UPGRADES AT RESTROOMS. "COMPLY WITH DEPARTMENT ORDER effective date 10/08/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/28/2025
Issuing Office
Current Status
Permit Finaled on 4/29/2026

Permit Application Status History

Submitted 4/11/2024 APPLICANT
Assigned to Plan Check Engineer 4/25/2024 MARVEL DELACRUZ
Corrections Issued 4/30/2024 MARVEL DELACRUZ
Quality Review Completed 5/1/2024 OMID HEDAYAT
Assigned to Zoning Architect 6/26/2024 CALEB WONG
Applicant returned to address corrections 8/1/2024 MARVEL DELACRUZ
Plan Check Approved 9/27/2024 MARVEL DELACRUZ
Issued 7/28/2025 APPLICANT
Permit Finaled 4/28/2026 BEHROUZ HASHEMI

Permit Application Clearance Information

"D" conditions Cleared 6/27/2024 ASHLEY RODARTE
"Q" conditions Cleared 7/3/2024 ASHLEY RODARTE
ZA Case Cleared 7/3/2024 ASHLEY RODARTE
Green Code Cleared 7/10/2024 MICHAEL AYERS
DAS Clearance Cleared 8/1/2024 Sergio Muniz
Zoning Plan Check Cleared 9/10/2024 CALEB WONG

Contact Information

Architect Anderson,, Shawn M; Lic. No.: NA31273       ,
Contractor Menemsha Development Group Inc; Lic. No.: 647870-B       ,
Engineer Adande, Kinti, Senase; Lic. No.: NA77492       ,

Inspector Information

BYRON BRASHEARS, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
TIM CROWDER, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
NEVILLE REID, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
BEHROUZ HASHEMI, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI
LINN MELVIN, (213) 252-3041 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/5/2025 Approved BEHROUZ HASHEMI
Interior/Exterior Lathing 11/7/2025 Partial Approval BEHROUZ HASHEMI
Pre-Inspection 11/7/2025 Approved BEHROUZ HASHEMI
Deputy Drilled-In Anchors 11/21/2025 Approved BEHROUZ HASHEMI
Excavation/Setback/Form/Re-Bar 11/21/2025 Approved BEHROUZ HASHEMI
Insulation 1/8/2026 Partial Approval BEHROUZ HASHEMI
Drywall Nailing 1/13/2026 Partial Approval BEHROUZ HASHEMI
Deputy Drilled-In Anchors 1/20/2026 Approved BEHROUZ HASHEMI
Reinforced Concrete Frame 1/21/2026 Approved BEHROUZ HASHEMI
Insulation 1/27/2026 Approved BEHROUZ HASHEMI
Drywall Nailing 2/3/2026 Approved BEHROUZ HASHEMI
Excavation/Setback/Form/Re-Bar 2/23/2026 Partial Approval BEHROUZ HASHEMI
Deputy Steel/Welding 2/24/2026 Approved BEHROUZ HASHEMI
Excavation/Setback/Form/Re-Bar 2/27/2026 Approved BEHROUZ HASHEMI
Drywall Nailing 3/12/2026 Approved BEHROUZ HASHEMI
Final 4/16/2026 Conditional Approval BEHROUZ HASHEMI
Final 4/21/2026 Not Ready for Inspection BEHROUZ HASHEMI
Final 4/28/2026 Permit Finaled BEHROUZ HASHEMI
Green Building Final 4/29/2026 Approved BEHROUZ HASHEMI
SGSOV-Seismic Gas S/O Valve 4/29/2026 SGSOV Not Required BEHROUZ HASHEMI