6412 1/2 N GOODLAND AVE 91606
Certificate Information: 6412 1/2 N GOODLAND AVE 91606
- Application / Permit
- 24016-20000-10567
- Plan Check / Job No.
- B24VN04173
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 29' 8" x 24' detached rec room to new ADU per CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 5/20/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2024 | NAREG ATARIAN |
| Corrections Issued | 4/16/2024 | NAREG ATARIAN |
| Quality Review Completed | 4/17/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/22/2024 | APPLICANT |
| Plan Check Approved | 5/20/2024 | NAREG ATARIAN |
| Issued | 5/20/2024 | APPLICANT |
| CofO in Progress | 12/5/2024 | GAREN HAYRAPETYAN |
| CofO in Progress | 12/9/2024 | RAUL OLAGI |
| CofO in Progress | 12/16/2024 | RAUL OLAGI |
| Permit Finaled | 12/18/2024 | RUBEN SALAS |
| CofO Issued | 12/18/2024 | RUBEN SALAS |
| Permit Finaled | 12/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2024 | CARLOS RAMIREZ |
| Construction near power lines | Cleared | 5/16/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/20/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 8/20/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Rough | 8/20/2024 | Not Ready for Inspection | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 9/3/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/3/2024 | Approved | OGANES TARAKHCHYAN |
| Rough-Elec/Plmb/HVAC | 9/3/2024 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 10/1/2024 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 10/7/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 10/7/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/7/2024 | Approved | OGANES TARAKHCHYAN |
| Underground Mechanical | 11/4/2024 | Approved | GAREN HAYRAPETYAN |
| Final | 12/5/2024 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 12/5/2024 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 12/5/2024 | Approved | GAREN HAYRAPETYAN |