20339-20341 W SUPERIOR ST 91311

Certificate Information: 20339-20341 W SUPERIOR ST 91311

Application / Permit
24016-20000-10553
Plan Check / Job No.
B24VN04162
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: Converting the exsiting attached gargage (448 sq.ft) to a ADU per state law WORK DONE PER WFPP
Permit Issued
Issued on 5/3/2024
Issuing Office
Current Status
CofO Issued on 9/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2024 APPLICANT
Assigned to Plan Check Engineer 4/2/2024 DANIEL SANJUAN
Corrections Issued 4/3/2024 DANIEL SANJUAN
Plan Check Approved 4/25/2024 KHUONG TRUONG
Issued 5/3/2024 APPLICANT
CofO in Progress 9/27/2024 DAVID SCANTLIN
CofO Issued 9/27/2024 JOHN JANSON
Permit Finaled 9/27/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/4/2024 CARLOS AGUILERA
Sewer availability Cleared 4/4/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/24/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/20/2024 Conditional Approval DAVID SCANTLIN
Footing/Foundation/Slab 6/25/2024 Approved DAVID SCANTLIN
PLUMBING-Rough 6/25/2024 Partial Approval DAVID SCANTLIN
ELECTRICAL-Rough 8/5/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 8/5/2024 Approved KRISTEN CAUSEY
Wood Frame 8/5/2024 Not Ready for Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Partial Approval ARUTYUN MADATYAN
Insulation 8/7/2024 Approved ARUTYUN MADATYAN
Drywall Nailing 8/12/2024 Not Ready for Inspection GEVORK IPCHYAN
Interior/Exterior Lathing 8/12/2024 Partial Approval GEVORK IPCHYAN
Shower Pan 8/12/2024 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 8/14/2024 Approved DAVID SCANTLIN
Drywall Nailing 8/14/2024 Approved DAVID SCANTLIN
Green Building Rough 8/14/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/14/2024 Approved DAVID SCANTLIN
ELECTRICAL-Final 9/16/2024 Approved DAVID SCANTLIN
Final 9/16/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 9/16/2024 Not Ready for Inspection DAVID SCANTLIN
HVAC-Final 9/16/2024 Approved DAVID SCANTLIN
PLUMBING-Final 9/16/2024 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 9/16/2024 SGSOV Approved DAVID SCANTLIN
Service/Power Release 9/16/2024 Approved DAVID SCANTLIN
Smoke Detectors 9/16/2024 Approved DAVID SCANTLIN
Final 9/27/2024 OK to Issue CofO DAVID SCANTLIN
Green Building Final 9/27/2024 Approved DAVID SCANTLIN