6025 N BUFFALO AVE 91401
Certificate Information: 6025 N BUFFALO AVE 91401
- Application / Permit
- 24016-20000-10546
- Plan Check / Job No.
- B24VN04155
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED GARAGE CONVERSION TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 5/14/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/3/2024 | JESSE ARELLANO |
| Corrections Issued | 4/4/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 4/8/2024 | APPLICANT |
| Applicant returned to address corrections | 5/1/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 5/3/2024 | MOHAMMAD ESMAILI |
| Issued | 5/14/2024 | APPLICANT |
| CofO in Progress | 11/20/2024 | OGANES TARAKHCHYAN |
| CofO in Progress | 11/20/2024 | RAUL OLAGI |
| CofO in Progress | 12/3/2024 | RAUL OLAGI |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
| CofO Issued | 12/14/2024 | RUBEN SALAS |
| Permit Finaled | 12/14/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/11/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 4/11/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 4/11/2024 | WALTER RAMIREZ |
| Sewer availability | Cleared | 4/11/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2024 | BIAINA HARITUNIAN |
| Metro Rail approval | Cleared | 4/23/2024 | JENNIFER SU |
Contact Information
| Contractor | Shay Designs; Lic. No.: 1073777-B | 6320 CANOGA AVE. SUITE 1500-#2315 WOODLAND HILLS, CA 91367 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/17/2024 | Approved | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 5/21/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/22/2024 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 6/25/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/25/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/25/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 6/25/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/15/2024 | No Access for Inspection | MISAEL ESPARZA |
| Wood Frame | 7/15/2024 | No Access for Inspection | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/17/2024 | Partial Approval | RYAN SALAZAR |
| Wood Frame | 7/17/2024 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 7/23/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 7/29/2024 | Not Ready for Inspection | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 7/29/2024 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 8/2/2024 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/21/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 10/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 10/23/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 10/23/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 11/6/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 11/6/2024 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 11/6/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 12/3/2024 | Corrections Issued | OGANES TARAKHCHYAN |