6025 N BUFFALO AVE 91401

Certificate Information: 6025 N BUFFALO AVE 91401

Application / Permit
24016-20000-10546
Plan Check / Job No.
B24VN04155
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DETACHED GARAGE CONVERSION TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 5/14/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/29/2024 APPLICANT
Assigned to Plan Check Engineer 4/3/2024 JESSE ARELLANO
Corrections Issued 4/4/2024 JESSE ARELLANO
Building Plans Picked Up 4/8/2024 APPLICANT
Applicant returned to address corrections 5/1/2024 SERGIO MUNIZ
Applicant returned to address corrections 5/3/2024 MOHAMMAD ESMAILI
Issued 5/14/2024 APPLICANT
CofO in Progress 11/20/2024 OGANES TARAKHCHYAN
CofO in Progress 11/20/2024 RAUL OLAGI
CofO in Progress 12/3/2024 RAUL OLAGI
Permit Finaled 12/14/2024 RUBEN SALAS
CofO Issued 12/14/2024 RUBEN SALAS
Permit Finaled 12/14/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/11/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 4/11/2024 WALTER RAMIREZ
Construction within easement Cleared 4/11/2024 WALTER RAMIREZ
Sewer availability Cleared 4/11/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/12/2024 BIAINA HARITUNIAN
Metro Rail approval Cleared 4/23/2024 JENNIFER SU

Contact Information

Contractor Shay Designs; Lic. No.: 1073777-B 6320 CANOGA AVE.   SUITE 1500-#2315    WOODLAND HILLS, CA 91367
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/17/2024 Approved OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 5/21/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/22/2024 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 6/25/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/25/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/25/2024 Approved OGANES TARAKHCHYAN
Wood Frame 6/25/2024 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 7/15/2024 No Access for Inspection MISAEL ESPARZA
Wood Frame 7/15/2024 No Access for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 7/17/2024 Partial Approval RYAN SALAZAR
Wood Frame 7/17/2024 Approved RYAN SALAZAR
BUILDING-Rough-Frame 7/23/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 7/23/2024 Approved OGANES TARAKHCHYAN
Insulation 7/23/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 7/29/2024 Not Ready for Inspection MICHAEL CORTEZ
Interior/Exterior Lathing 7/29/2024 Approved MICHAEL CORTEZ
Drywall Nailing 8/2/2024 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/21/2024 SGSOV Not Ready OGANES TARAKHCHYAN
Final 10/23/2024 Corrections Issued OGANES TARAKHCHYAN
Green Building Final 10/23/2024 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 10/23/2024 Approved OGANES TARAKHCHYAN
Final 11/6/2024 OK to Issue CofO OGANES TARAKHCHYAN
Green Building Final 11/6/2024 Approved OGANES TARAKHCHYAN
Service/Power Release 11/6/2024 Approved OGANES TARAKHCHYAN
Final 12/3/2024 Corrections Issued OGANES TARAKHCHYAN