16730-16732 W SEPTO ST 91343

Certificate Information: 16730-16732 W SEPTO ST 91343

Application / Permit
24016-20000-10327
Plan Check / Job No.
B24VN04052
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan. Convert (E) Attached Garage to (N) ADU per CA Govt. Code 65852.2(e)(1)(A). All work per WFPP
Permit Issued
Issued on 5/4/2024
Issuing Office
Current Status
CofO Issued on 10/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/28/2024 APPLICANT
Assigned to Plan Check Engineer 4/2/2024 AMY GUEVARRA
Corrections Issued 4/3/2024 AMY GUEVARRA
Plan Check Approved 5/3/2024 CAROLEAN BASMA
Issued 5/4/2024 APPLICANT
CofO in Progress 8/27/2024 ROBERT GOLD
Permit Finaled 10/12/2024 DANIEL ORRANTE
CofO Issued 10/12/2024 DANIEL ORRANTE
Permit Finaled 10/12/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/19/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 4/19/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/19/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 4/19/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 4/22/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/20/2024 Partial Inspection JAVIER RAMOS JR
Deputy Drilled-In Anchors 5/20/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 5/20/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 5/20/2024 Partial Approval JAVIER RAMOS JR
Interior/Exterior Lathing 5/20/2024 Partial Inspection JAVIER RAMOS JR
PLUMBING-Rough 5/20/2024 Partial Approval JAVIER RAMOS JR
Sewer 5/20/2024 Approved JAVIER RAMOS JR
Underground Mechanical 5/20/2024 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 5/22/2024 Partial Inspection JAVIER RAMOS JR
Footing/Foundation/Slab 5/22/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/22/2024 Partial Approval JAVIER RAMOS JR
Shower Pan 5/22/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 5/24/2024 Approved JAVIER RAMOS JR
HVAC-Rough 5/24/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 5/24/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 5/28/2024 Approved KEVIN BERBERYAN
Insulation 5/28/2024 Approved KEVIN BERBERYAN
Drywall Nailing 5/29/2024 Approved JAVIER RAMOS JR
Green Building Final 7/8/2024 Approved JAVIER RAMOS JR
Pre-Inspection 7/8/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Final 7/10/2024 Approved JAVIER RAMOS JR
Final 7/10/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Final 7/10/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 7/10/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/10/2024 SGSOV Not Ready JAVIER RAMOS JR
Service/Power Release 7/10/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 7/10/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 8/13/2024 Approved JAVIER RAMOS JR
Final 8/13/2024 OK to Issue CofO JAVIER RAMOS JR
Green Building Rough 8/13/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 8/13/2024 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 8/13/2024 Approved JAVIER RAMOS JR