16513-16515 W TUPPER ST 91343

Certificate Information: 16513-16515 W TUPPER ST 91343

Application / Permit
24016-20000-10181
Plan Check / Job No.
B24VN03991
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Attached Garage Conversion to ADU per GCS 65852.2(e)(1)(A) in an (E) 1-Story SFD
Permit Issued
Issued on 5/7/2024
Issuing Office
Current Status
CofO Issued on 11/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/26/2024 APPLICANT
Assigned to Plan Check Engineer 3/29/2024 DAVID CASTILLO
Corrections Issued 3/30/2024 DAVID CASTILLO
Applicant returned to address corrections 4/25/2024 DAVID CASTILLO
Plan Check Approved 5/2/2024 CAROLEAN BASMA
Issued 5/7/2024 APPLICANT
CofO in Progress 10/29/2024 SALVADOR MARTINEZ
Permit Finaled 11/15/2024 DANIEL ORRANTE
CofO Issued 11/15/2024 DANIEL ORRANTE
Permit Finaled 11/15/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/15/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 4/15/2024 CARLOS RAMIREZ
Sewer availability Cleared 4/15/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 4/22/2024 CARLOS RAMIREZ
Grading Pre-Inspection Cleared 4/29/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez,, Jose Antonio; Lic. No.: C69472 3557 E 58TH ST      MAYWOOD, CA 90270

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/5/2024 Conditional Approval RAUL OLAGI
Deputy Drilled-In Anchors 6/6/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 6/10/2024 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 6/10/2024 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 6/12/2024 Corrections Issued RAUL OLAGI
PLUMBING-Rough 6/12/2024 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 6/17/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 7/1/2024 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 7/22/2024 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 7/22/2024 Corrections Issued RAUL OLAGI
HVAC-Rough 7/22/2024 Approved RAUL OLAGI
PLUMBING-Rough 7/22/2024 Corrections Issued RAUL OLAGI
Sewer 7/22/2024 Approved RAUL OLAGI
ELECTRICAL-Rough 7/29/2024 Approved RAUL OLAGI
Green Building Rough 7/29/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 7/29/2024 Partial Approval RAUL OLAGI
PLUMBING-Rough 7/29/2024 Approved RAUL OLAGI
BUILDING-Rough-Frame 8/5/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Approved JENNIFER RABUCHIN
Insulation 8/5/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 8/12/2024 Approved RAUL OLAGI
Shower Pan 8/12/2024 Approved RAUL OLAGI
Interior/Exterior Lathing 8/26/2024 Approved RAUL OLAGI
Final 10/1/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 10/1/2024 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved SALVADOR MARTINEZ
Smoke Detectors 10/1/2024 Approved SALVADOR MARTINEZ
Final 10/16/2024 Corrections Issued SALVADOR MARTINEZ
Green Building Final 10/16/2024 Approved SALVADOR MARTINEZ
Final 10/22/2024 OK to Issue CofO SALVADOR MARTINEZ
Special/Order Compliance 10/22/2024 Partial Inspection RAUL OLAGI