16513-16515 W TUPPER ST 91343
Certificate Information: 16513-16515 W TUPPER ST 91343
- Application / Permit
- 24016-20000-10181
- Plan Check / Job No.
- B24VN03991
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Attached Garage Conversion to ADU per GCS 65852.2(e)(1)(A) in an (E) 1-Story SFD
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- CofO Issued on 11/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | DAVID CASTILLO |
| Corrections Issued | 3/30/2024 | DAVID CASTILLO |
| Applicant returned to address corrections | 4/25/2024 | DAVID CASTILLO |
| Plan Check Approved | 5/2/2024 | CAROLEAN BASMA |
| Issued | 5/7/2024 | APPLICANT |
| CofO in Progress | 10/29/2024 | SALVADOR MARTINEZ |
| Permit Finaled | 11/15/2024 | DANIEL ORRANTE |
| CofO Issued | 11/15/2024 | DANIEL ORRANTE |
| Permit Finaled | 11/15/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/15/2024 | CARLOS RAMIREZ |
| Roof/Waste drainage to street | Cleared | 4/15/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 4/15/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | CARLOS RAMIREZ |
| Grading Pre-Inspection | Cleared | 4/29/2024 | CHARLES POWELL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Jose Antonio; Lic. No.: C69472 | 3557 E 58TH ST MAYWOOD, CA 90270 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/5/2024 | Conditional Approval | RAUL OLAGI |
| Deputy Drilled-In Anchors | 6/6/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 6/10/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 6/12/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 6/12/2024 | Partial Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 6/17/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/1/2024 | Not Ready for Inspection | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/22/2024 | Corrections Issued | RAUL OLAGI |
| ELECTRICAL-Rough | 7/22/2024 | Corrections Issued | RAUL OLAGI |
| HVAC-Rough | 7/22/2024 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 7/22/2024 | Corrections Issued | RAUL OLAGI |
| Sewer | 7/22/2024 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 7/29/2024 | Approved | RAUL OLAGI |
| Green Building Rough | 7/29/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/29/2024 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 7/29/2024 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 8/5/2024 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2024 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/5/2024 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/12/2024 | Approved | RAUL OLAGI |
| Shower Pan | 8/12/2024 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 8/26/2024 | Approved | RAUL OLAGI |
| Final | 10/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 10/1/2024 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 10/1/2024 | Approved | SALVADOR MARTINEZ |
| Final | 10/16/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 10/16/2024 | Approved | SALVADOR MARTINEZ |
| Final | 10/22/2024 | OK to Issue CofO | SALVADOR MARTINEZ |
| Special/Order Compliance | 10/22/2024 | Partial Inspection | RAUL OLAGI |