9705-9707 N ORION AVE 91343
Certificate Information: 9705-9707 N ORION AVE 91343
- Application / Permit
- 24016-20000-10174
- Plan Check / Job No.
- B24VN03986
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan. Convert existing attached garage to attached ADU. Work per WFPP.
- Permit Issued
- Issued on 5/17/2024
- Issuing Office
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2024 | ADAM HEGAZI |
| Corrections Issued | 4/3/2024 | ADAM HEGAZI |
| Applicant returned to address corrections | 4/24/2024 | JOSE VELAZQUEZ |
| Applicant returned to address corrections | 4/28/2024 | NGHI SU |
| Plan Check Approved | 5/1/2024 | NGHI SU |
| Issued | 5/17/2024 | APPLICANT |
| CofO in Progress | 3/25/2025 | VINCENT HANLEY |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
| CofO Issued | 4/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/8/2024 | BIAINA HARITUNIAN |
| ZA Case | Cleared | 4/17/2024 | ALEX VELA |
Contact Information
| Contractor | O D Solutions Remodeling & Construction Inc; Lic. No.: 1105993-B | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/30/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 8/8/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 8/8/2024 | Partial Approval | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 8/8/2024 | SGSOV Not Ready | VINCENT HANLEY |
| Sewer | 8/8/2024 | Approved | VINCENT HANLEY |
| Underground Mechanical | 8/8/2024 | Partial Approval | VINCENT HANLEY |
| Footing/Foundation/Slab | 8/13/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/23/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/23/2024 | Corrections Issued | VINCENT HANLEY |
| Green Building Rough | 9/23/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 9/23/2024 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Rough | 9/23/2024 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 9/23/2024 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/1/2024 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/1/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/1/2024 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 10/1/2024 | Corrections Issued | VINCENT HANLEY |
| MERV13>=Rough | 10/1/2024 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 10/1/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/4/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 10/4/2024 | Approved | VINCENT HANLEY |
| Insulation | 10/4/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/4/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/9/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/9/2024 | Approved | VINCENT HANLEY |
| Shower Pan | 10/9/2024 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 2/28/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 2/28/2025 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/28/2025 | Approved | VINCENT HANLEY |
| MERV13>=Final | 2/28/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/28/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/28/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 3/10/2025 | Approved | VINCENT HANLEY |
| Final | 3/10/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 3/10/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/10/2025 | Approved | VINCENT HANLEY |
| Service/Power Release | 3/10/2025 | Approved | VINCENT HANLEY |
| Final | 3/24/2025 | OK to Issue CofO | VINCENT HANLEY |