14808 W COVELLO ST 91405
Certificate Information: 14808 W COVELLO ST 91405
- Application / Permit
- 24016-20000-10085
- Plan Check / Job No.
- B24VN03935
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 9/17/2024
- Issuing Office
- Current Status
- CofO Issued on 5/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/29/2024 | JESSE ARELLANO |
| Corrections Issued | 3/30/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 4/1/2024 | APPLICANT |
| Plan Check Approved | 9/17/2024 | SERGIO MUNIZ |
| Issued | 9/17/2024 | APPLICANT |
| CofO in Progress | 5/15/2025 | VINCENT HANLEY |
| CofO Issued | 5/21/2025 | RUBEN SALAS |
| Permit Finaled | 5/21/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/5/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 4/5/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2024 | BRYAN GODINEZ |
| Construction near power lines | Cleared | 9/13/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/22/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 1/28/2025 | Approved | MATTHEW NELSON |
| Underground Mechanical | 1/28/2025 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 2/28/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/28/2025 | Approved | VINCENT HANLEY |
| Final | 2/28/2025 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2025 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 2/28/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/28/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/28/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 2/28/2025 | Approved | VINCENT HANLEY |
| Gas Test | 3/14/2025 | Not Ready for Inspection | WILLIAM WREN |
| Sewer | 3/14/2025 | Not Ready for Inspection | WILLIAM WREN |
| Underground Mechanical | 3/14/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 3/21/2025 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2025 | Approved | VINCENT HANLEY |
| Green Building Final | 3/21/2025 | Approved | VINCENT HANLEY |
| Insulation | 3/21/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 3/21/2025 | Approved | VINCENT HANLEY |
| Drywall Nailing | 3/25/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 3/25/2025 | Approved | VINCENT HANLEY |
| Final | 5/6/2025 | Corrections Issued | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 5/6/2025 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 5/6/2025 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/14/2025 | Approved | VINCENT HANLEY |
| Final | 5/14/2025 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 5/14/2025 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/14/2025 | Approved | VINCENT HANLEY |