9301-9303 N WYSTONE AVE 91324

Certificate Information: 9301-9303 N WYSTONE AVE 91324

Application / Permit
24016-20000-09860
Plan Check / Job No.
B24VN03849
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: CONVERT (E) 20' x 20' ATTACHED GARAGE TO A NEW ATTACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER ENGINEER DEISGN.
Permit Issued
Issued on 4/15/2024
Issuing Office
Current Status
CofO Issued on 1/2/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2024 APPLICANT
Assigned to Plan Check Engineer 3/29/2024 MIROOSH KHACHATOORIAN
Corrections Issued 4/1/2024 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 4/9/2024 MIROOSH KHACHATOORIAN
Plan Check Approved 4/12/2024 MIROOSH KHACHATOORIAN
Issued 4/15/2024 APPLICANT
CofO in Progress 11/12/2024 KRISTEN BEVERIDGE
Permit Finaled 1/2/2025 JOHN JANSON
CofO Issued 1/2/2025 JOHN JANSON
Permit Finaled 1/2/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/5/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/5/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Gosen,, James; Lic. No.: C43590 15315 BLEDSOE ST      SYLMAR, CA 91342

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/4/2024 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 6/6/2024 Approved KRISTEN CAUSEY
ELECTRICAL-Rough 7/31/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 7/31/2024 Not Ready for Inspection DAVID SCANTLIN
Underground Mechanical 7/31/2024 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 8/1/2024 Approved KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 8/7/2024 Approved KRISTEN CAUSEY
PLUMBING-Rough 8/7/2024 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 8/12/2024 Approved DAVID SCANTLIN
Green Building Rough 8/12/2024 Approved DAVID SCANTLIN
Insulation 8/12/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 8/12/2024 Partial Approval DAVID SCANTLIN
Drywall Nailing 8/20/2024 Approved KRISTEN CAUSEY
Shower Pan 8/20/2024 Approved KRISTEN CAUSEY
Final 10/15/2024 Corrections Issued KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Approved KRISTEN CAUSEY
Smoke Detectors 10/15/2024 Approved KRISTEN CAUSEY
Final 11/8/2024 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 11/8/2024 Approved KRISTEN CAUSEY