7048 N MCLAREN AVE 91307

Certificate Information: 7048 N MCLAREN AVE 91307

Application / Permit
24016-20000-09595
Plan Check / Job No.
B24VN03739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN. REMODEL (E) SFD PER ENGINEER'S DESIGN
Permit Issued
Issued on 4/9/2024
Issuing Office
Current Status
Permit Finaled on 7/15/2024

Permit Application Status History

Submitted 3/27/2024 APPLICANT
Assigned to Plan Check Engineer 3/27/2024 AMY GUEVARRA
Corrections Issued 3/31/2024 AMY GUEVARRA
Plan Check Approved 4/5/2024 AMY GUEVARRA
Issued 4/9/2024 APPLICANT
Permit Finaled 7/12/2024 JEFFREY HARTLINE

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor The Josefzon Group; Lic. No.: 1064933-B 22287 MULHOLLAND HWY #614      CALABASAS, CA 91302
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/23/2024 Approved JEFFREY HARTLINE
Footing/Foundation/Slab 4/23/2024 Approved JEFFREY HARTLINE
Underground Mechanical 4/29/2024 Approved JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/13/2024 Partial Approval JEFFREY HARTLINE
HVAC-Rough 5/13/2024 Approved JEFFREY HARTLINE
PLUMBING-Rough 5/13/2024 Corrections Issued JEFFREY HARTLINE
ELECTRICAL-Rough 5/21/2024 Not Ready for Inspection JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 5/21/2024 Partial Approval JEFFREY HARTLINE
Interior/Exterior Lathing 5/21/2024 Partial Approval JEFFREY HARTLINE
PLUMBING-Rough 5/21/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 5/28/2024 Approved ROBERT CORNELL
Insulation 5/30/2024 Approved JEFFREY HARTLINE
Interior/Exterior Lathing 5/30/2024 Approved JEFFREY HARTLINE
Shower Pan 5/30/2024 Approved JEFFREY HARTLINE
Drywall Nailing 6/5/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 7/5/2024 Corrections Issued JEFFREY HARTLINE
HVAC-Final 7/5/2024 Corrections Issued JEFFREY HARTLINE
PLUMBING-Final 7/5/2024 Approved JEFFREY HARTLINE
SGSOV-Seismic Gas S/O Valve 7/5/2024 SGSOV Approved JEFFREY HARTLINE
Smoke Detectors 7/5/2024 Approved JEFFREY HARTLINE
ELECTRICAL-Final 7/12/2024 Approved JEFFREY HARTLINE
Final 7/12/2024 Permit Finaled JEFFREY HARTLINE