8544-8546 N WISNER AVE 91343

Certificate Information: 8544-8546 N WISNER AVE 91343

Application / Permit
24016-20000-09350
Plan Check / Job No.
B24VN03697
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE INTO A (N) JUNIOR ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) AND 65852.22 PER WFPP
Permit Issued
Issued on 3/7/2025
Issuing Office
Current Status
CofO Issued on 9/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 ALFRED RAMIREZ
Corrections Issued 3/28/2024 ALFRED RAMIREZ
Building Plans Picked Up 4/4/2024 APPLICANT
Plan Check Approved 3/7/2025 ALEC MOUSAKHANIAN
Issued 3/7/2025 APPLICANT
CofO in Progress 9/12/2025 VINCENT HANLEY
Permit Finaled 9/24/2025 RUBEN SALAS
CofO Issued 9/24/2025 RUBEN SALAS
Permit Finaled 9/24/2025 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 12/9/2024 RIDWAN HARDY
Construction within easement Cleared 12/9/2024 RIDWAN HARDY
Address approval Cleared 1/3/2025 CARLOS AGUILERA
Sewer availability Cleared 1/3/2025 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/13/2025 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/30/2025 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 5/5/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 5/5/2025 Approved VINCENT HANLEY
PLUMBING-Rough 5/20/2025 Approved VINCENT HANLEY
Sewer 5/20/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/22/2025 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 5/22/2025 Partial Approval MICHEL ABAJAN
ELECTRICAL-Rough 5/28/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Approved VINCENT HANLEY
Insulation 5/28/2025 Partial Approval VINCENT HANLEY
HVAC-Rough 6/5/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/10/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Approved VINCENT HANLEY
Insulation 6/10/2025 Approved VINCENT HANLEY
Drywall Nailing 6/24/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 6/24/2025 Approved LOUIS ESCOTO
Shower Pan 6/24/2025 Approved LOUIS ESCOTO
Gas Test 8/8/2025 Approved LOUIS ESCOTO
ELECTRICAL-Rough 8/26/2025 Approved VINCENT HANLEY
Final 8/26/2025 Corrections Issued VINCENT HANLEY
HVAC-Final 8/26/2025 Approved VINCENT HANLEY
PLUMBING-Final 8/26/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/26/2025 SGSOV Approved VINCENT HANLEY
Service/Power Release 8/26/2025 Approved VINCENT HANLEY
Smoke Detectors 8/26/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 9/11/2025 Approved VINCENT HANLEY
Final 9/11/2025 OK to Issue CofO VINCENT HANLEY