328 S WINDSOR BLVD 90020

Certificate Information: 328 S WINDSOR BLVD 90020

Application / Permit
24016-20000-09347
Plan Check / Job No.
B24VN03691
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) TWO STORY ACCESSORY LIVING QUARTERS / GARAGE TO (N) 1303 SF ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
Permit Issued
Issued on 5/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/19/2024 APPLICANT
Assigned to Plan Check Engineer 3/28/2024 GIOVANNY CHAVEZ
Corrections Issued 3/28/2024 GIOVANNY CHAVEZ
Building Plans Picked Up 3/28/2024 APPLICANT
Applicant returned to address corrections 4/19/2024 GIOVANNY CHAVEZ
Plan Check Approved 5/23/2024 LUISANGEL VALENZUELA
Issued 5/23/2024 APPLICANT
CofO in Progress 2/18/2025 JEFFREY MEAD
No Progress 2/21/2025 JEFFREY MEAD
CofO in Progress 2/21/2025 JEFFREY MEAD
CofO in Progress 5/13/2025 RAUL BARAJAS
Permit Finaled 5/18/2025 DEROLD HAUFF
CofO Issued 5/18/2025 DEROLD HAUFF
Permit Finaled 5/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/26/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 4/26/2024 CELINA MORENO
Sewer availability Cleared 4/26/2024 CELINA MORENO
HPOZ Cleared 5/17/2024 DAMIAN GATTO

Contact Information

Contractor E I G Management; Lic. No.: 1034806-B 15165 VENTURA BLVD STE 315      SHERMAN OAKS, CA 91403
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/3/2024 Partial Approval JEFFREY MEAD
Footing/Foundation/Slab 6/4/2024 Corrections Issued JEFFREY MEAD
Underground Mechanical 6/11/2024 Approved JEFFREY MEAD
Deputy Drilled-In Anchors 6/18/2024 Approved JEFFREY MEAD
Footing/Foundation/Slab 6/18/2024 Partial Approval JEFFREY MEAD
ELECTRICAL-Rough 9/5/2024 Corrections Issued ENRIQUE MIRELES
HVAC-Rough 9/5/2024 Not Ready for Inspection ENRIQUE MIRELES
PLUMBING-Rough 9/5/2024 Not Ready for Inspection ENRIQUE MIRELES
ELECTRICAL-Rough 9/9/2024 Corrections Issued JEFFREY MEAD
HVAC-Rough 9/9/2024 Approved JEFFREY MEAD
PLUMBING-Rough 9/9/2024 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 9/19/2024 Approved JEFFREY MEAD
PLUMBING-Rough 9/19/2024 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 9/24/2024 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 9/24/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 9/26/2024 Approved JEFFREY MEAD
Deputy Wood Construction 9/26/2024 Partial Approval JEFFREY MEAD
Green Building Rough 9/26/2024 Approved JEFFREY MEAD
Insulation 9/26/2024 Approved JEFFREY MEAD
METHANE-Rough 9/26/2024 Approved JEFFREY MEAD
Drywall Nailing 9/30/2024 Corrections Issued JEFFREY MEAD
Interior/Exterior Lathing 9/30/2024 Not Ready for Inspection JEFFREY MEAD
Shower Pan 9/30/2024 Not Ready for Inspection JEFFREY MEAD
Drywall Nailing 10/7/2024 Approved JEFFREY MEAD
Interior/Exterior Lathing 10/7/2024 Approved JEFFREY MEAD
Shower Pan 10/7/2024 Approved JEFFREY MEAD
ELECTRICAL-Rough 10/15/2024 Corrections Issued JEFFREY MEAD
Sewer 10/15/2024 Approved JEFFREY MEAD
Final 2/5/2025 Corrections Issued JEFFREY MEAD
Green Building Final 2/5/2025 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 2/5/2025 SGSOV Not Required JEFFREY MEAD
Smoke Detectors 2/5/2025 Approved JEFFREY MEAD
Final 2/12/2025 Corrections Issued JEFFREY MEAD
Final 2/18/2025 OK to Issue CofO JEFFREY MEAD
Special/Order Compliance 2/21/2025 Corrections Issued JEFFREY MEAD
Final 5/12/2025 OK to Issue CofO RAUL BARAJAS