16042-16044 W KNAPP ST 91343
Certificate Information: 16042-16044 W KNAPP ST 91343
- Application / Permit
- 24016-20000-09341
- Plan Check / Job No.
- B24VN03687
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO A NEW ATTACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK DONE PER WFPP.
- Permit Issued
- Issued on 4/4/2024
- Issuing Office
- Current Status
- Issued on 4/4/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/28/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 3/28/2024 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 4/2/2024 | APPLICANT |
| Applicant returned to address corrections | 4/4/2024 | ALEC MOUSAKHANIAN |
| Issued | 4/4/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 4/4/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/4/2024 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 4/4/2024 | MANUEL TEJADA |
| Sewer availability | Cleared | 4/4/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Final | 7/23/2026 Time Frame: 1-3 |
| Smoke Detectors | 7/23/2026 Time Frame: 1-3 |
| Green Building Final | 7/23/2026 Time Frame: 1-3 |
Inspection Request History
| Pre-Inspection | 12/6/2024 | Approved | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 9/24/2025 | Approved | GAREN HAYRAPETYAN |
| Underground Mechanical | 9/24/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Deputy Drilled-In Anchors | 10/8/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2025 | Partial Approval | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/13/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 12/4/2025 | Approved | CHRISTOPHER MORFIN |
| Interior/Exterior Lathing | 12/4/2025 | Partial Approval | CHRISTOPHER MORFIN |
| Drywall Nailing | 2/2/2026 | Partial Approval | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/2/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 2/4/2026 | Approved | MICHAEL CORTEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2026 | Approved | MICHAEL CORTEZ |
| Green Building Rough | 2/4/2026 | Approved | MICHAEL CORTEZ |
| BUILDING-Rough-Frame | 6/16/2026 | Approved | MICHAEL CORTEZ |
| Final | 6/16/2026 | Corrections Issued | MICHAEL CORTEZ |
| Green Building Final | 6/16/2026 | Corrections Issued | MICHAEL CORTEZ |
| SGSOV-Seismic Gas S/O Valve | 6/16/2026 | SGSOV Not Required | MICHAEL CORTEZ |
| Smoke Detectors | 6/16/2026 | Corrections Issued | MICHAEL CORTEZ |