7451-7453 N IRVINE AVE 91605
Certificate Information: 7451-7453 N IRVINE AVE 91605
- Application / Permit
- 24016-20000-09151
- Plan Check / Job No.
- B24VN03610
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. CONVERT (E) ATACHED GARAGE TO ADU PER STATE LAW
- Permit Issued
- Issued on 5/16/2024
- Issuing Office
- Current Status
- CofO Issued on 5/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/18/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 3/22/2024 | MINA HABILI |
| Corrections Issued | 3/23/2024 | MINA HABILI |
| Applicant returned to address corrections | 5/3/2024 | MINA HABILI |
| Applicant returned to address corrections | 5/13/2024 | KELVIN CHUONG |
| Plan Check Approved | 5/16/2024 | KELVIN CHUONG |
| Issued | 5/16/2024 | APPLICANT |
| CofO in Progress | 4/15/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
| CofO Issued | 5/13/2025 | RUBEN SALAS |
| Permit Finaled | 5/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 4/23/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Dong,, Truong Tan; Lic. No.: C75466 | 10692 SILVER CIRCLE GARDEN GROVE, CA 92843 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/22/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Sewer | 7/22/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/8/2024 | Corrections Issued | RYAN SALAZAR |
| Sewer | 8/8/2024 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 8/12/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 8/12/2024 | Partial Approval | JOSE AVILA |
| Wood Frame | 9/6/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 10/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 10/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 10/17/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 10/17/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/17/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Insulation | 10/17/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 10/17/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/17/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 11/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 2/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 2/20/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 2/21/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 3/19/2025 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 3/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 3/26/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 3/26/2025 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 3/26/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 3/28/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/2/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 4/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/8/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/8/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/15/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 4/15/2025 | Approved | ROBERTO PALACIOS-LOPEZ |